TURNOVER PROTOCOL - STEP BY STEP PROCEDURE
STEP TITLE DESCRIPTION
TURNOVER
DOCUMENTS
APPEN-
DICES
5 Construction Kickoff
meeting.
DGS-PM shall invite Turnover Manager to the
Construction Kick–Off Meeting. FTM shall be
provided with the construction schedule. GC shall
advise Progress Meeting schedule
6 Pre Close-In
Walkthrough.
At appropriate times during construction, DGS-PM
shall invite Turnover Manager to a walkthrough of
the project to allow Facilities staff to observe and
familiarize themselves with the as-built condition of
building systems, prior to close-in, and comment on
any noted concerns.
A.
7 Notify Turnover
Manager of
Commissioning
Schedule.
Once active commissioning is scheduled FTM shall
be advised, so Facilities can observe per their
requirements. DGS-PM should provide the
completed Equipment List at this time.
Equipment List
B.
8 Schedule Closeout
Conference
On larger projects, DGS-PM shall schedule a
Project Closeout Conference when the DGS-PM
Team deem it adventagous.
Invitee's should include FTM, CTM, A-E, Client
Agency Rep.and, at GC's discretion, major sub-
contractors. Schedule with sufficient time to help
GC prepare for requesting Substantial Completion.
Turnover Checklist
Base
9 Schedule Training
Sessions.
DGS-PM shall invite Turnover Manager to all
training sessions required by the contract
documents, (or requested by FTM based on scope
of work). Provide Turnover Manager with a
minimum of five working days’ notice to allow
Facilities to schedule the correct personnel. All
training sessions shall be recorded. Include sign-in
sheet
A.
C.
10 Pre-Substantial
Completion Final
Punch List Walk
DGS-PM shall invite the Turnover Manager and
Punch list Manager. (Following the contractors
written request for Substantial Completion in
accordance with specification section 017700)
Request for
Substantial
Completion Letter
A.
11 Process Certificate of
Substantial
Completion.
DGS-PM shall review the documents provided by
the Contractor, mark up the Pre-Substantial
Completion Section of Turnover Checklist and
provide to CTM for verification. DGS-PM and
CTM shall process the Certificate of Substantial
Completion.
Certificate of
Substantial
Completion
D.
E.
F.
G.
H.
12 Process Final
Completion
Documents
DGS-PM shall review the documents provided by
the Contractor, mark up the Pre-Final Completion
section of the Turnover Checklist and provide to
CTM for verification.
G.
H.
I.
CONSTRUCTION PHASE
Update 03/08/24 5