McKenna Government Contracts,
continuing excellence at Dentons
Request for Equitable Adjustment
(REA) and Claim Pricing
1
January 12, 2016
Disputes Process Overview
Claim v. REA
Basic Entitlement Theories
Pricing Considerations
Methodologies
Application to REA/Claim Types
Pricing Added/Deleted Work
Overhead and Profit Issues
Special Situations (e.g., subcontractor pricing issues)
Recent Developments
Best Practices for Development, Pricing, Negotiating, and Resolving
REAs and Claims
2
Agenda
Request for Equitable Adjustment (REA): a “Proposal” for Additional
Compensation as a Result of Certain Circumstances or Government
Conduct
Examples:
Changes Clause (FAR § 52.243-1): CO “Shall Make an Equitable Adjustment”
Differing Site Conditions (FAR § 52.236-2): “[A]n equitable adjustment shall be made” if differing
site conditions increase Contractor’s cost.
Government Property (FAR § 52.245-1): For unsuitable government property, CO “shall consider
an equitable adjustment.”
Suspension of Work (FAR § 52.242-14): “[A]n adjustment shall be made” for CO actions that delay
and increase the cost of performance.
DoD Requires Contractors to Certify REAs are Submitted “In Good Faith”
and “Supporting Data are Accurate and Complete.” DFARS § 252.243-
7002
TINA Certification may be Required if REA Valued Above $750,000, the
Contract is Non-Commercial, and Contract Price will be Modified.
3
REA Overview
Contract Disputes Act (CDA), 41 U.S.C. §7101 et seq.; FAR Subpart
33.2
Governs Disputes “Arising Under” or “Related to” a Government Contract
Certified Claim to the CO
A Non-Routine “Written Demand or Written Assertion”
“Seeking, as a Matter of Right”
“Payment of Money in a Sum Certain, the Adjustment or Interpretation of Contract Terms, or
Other Relief”
CDA Certifications:
FAR § 52.233-1, CDA Certification: Claims Exceeding $100,000
Elements: Claim is made in good faith; supporting data is accurate and complete to the best of the
Contractor’s knowledge and belief; the amount requested accurately reflects the contract
adjustment for which the Contractor believes the Government is liable; the person submitting the
claim is authorized to certify the claim on the Contractor’s behalf
Proper Certifying Official
4
CDA Overview
Basic Legal Entitlement Grounds:
Constructive Changes/Scope Changes
Added or deleted work absent a change order
Improper contract interpretation
Defective specifications
Superior government knowledge
Interference/failure to cooperate/bad faith
Unreasonable inspection/acceptance
Stop Work Orders/Government Suspension of Work
Government Delay/Acceleration
Government Property
Differing site condition
Value Engineering
5
REA/ClaimsLegal Entitlement Theories
CDA Claims v. REAs
6
Contract Administration v. Prosecution of Claims
General rule: REA costs may be allowable; Claim costs
generally unallowable
REA Costs
Tip Top Constr., Inc. v. Donahoe, 695 F.3d 1276 (Fed. Cir. 2012)
Fees associated with “the realm of negotiation and genuine contract administration” are allowable,
even if negotiations fail and result in a claim
Moshe Safdie & Assocs., Inc. v. Gen. Servs. Admin., CBCA 1849, 14-1 BCA 35,564
(Mar. 13, 2014)
REA preparation costs are allowable
See also Bill Strong Enterprises, Inc. v. Shannon, 49 F.3d 1541, 1550-51 (Fed Cir.
1995) overruled on other grounds, Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir.,
1995).
Claim Costs
FAR§31.205-47 disallows costs associated with both prosecution and defense of non-
fraud CDA claims
7
Allowability of REA Costs v. Claim Costs
Done Last/Reviewed First
Pricing Drives the Decision-Making Process
Government Often Ignores Entitlement and Defends Claim with Attack on
the Amount Claimed
Requires Coordinated Cross-Functional Team Effort
Contractor Risks
False Claims/Fraud
Defective Pricing/TINA
Disapproval of Estimating System, Possibly Others
8
Importance of REA/Claim Pricing
Objective: Calculate the Increased Cost of the Changed Work
Place Contractor in Same Profit or Loss Position as If No Change Occurred
Fundamentally Cost-Based Pricing
Generally broken out into four components:
Calculation of costs directly attributable to added work
Includes increased costs based on constructive changes
Calculation of costs directly attributable to eliminated work
Calculating overhead and profit for costs attributable to changed work
Contract administration costs
Reasonable Cost, Not Value
No Presumption of Reasonableness
9
General Pricing Considerations
FAR § 15.408, Table 15-2 III(B) Provides Guidance Relating to Change Order, Modification
and Claim Pricing
FAR Part 31 Applies to Contract Modifications; However, Application Must Result in
“Equitable Adjustment”
Reasonableness
Allocability
Conformity with Cost Accounting Standards (CAS), if applicable, GAAP and circumstances
Consistent with terms of the Contract
Conformity with limitations of FAR Subpart 31.2
Contractor Burden of Proof: (1) Entitlement, (2) Causation, and (3) Amount/Quantum
Amount: No Need for Absolute Certainty—“Reasonable Basis”:
BPLW Architects & Engineers, Inc. v. United States, 106 Fed. Cl. 521, 544 (2012) (“The amount of
damages may be approximated, but only if a reasonable basis of computation is afforded.”) (internal
quotation marks omitted).
Tension with fraud cases: when do a contractor’s unreasonably calculated damages
constitute a false claim?
10
General Pricing Considerations (Cont.)
Forfeiture
Claim is forfeited if claimant attempts to defraud the government with the claim.
28 U.S.C. § 2514. See also Daewoo Engineering and Construction Co. Ltd. v. United States, 557
F.3d 1332 (Fed. Cir. 2009) (entire claim can be forfeited when part of claim was fraudulently inflated
as a “negotiating ploy”); Horn & Associates, Inc. v. US, 123 Fed. Cl. 728 (2015) (any fraudulent
invoice submitted during contract performance may waive later claim).
Jurisdiction
Exclusive jurisdiction vested in Court of Federal Claims to render judgment of forfeiture. 28 U.S.C.
§ 2514.
Board has no jurisdiction to hear the fraud case.
Board may but need not dismiss a claim pending resolution of the fraud case.
Compare KBR, Inc., ASBCA No. 57530, 13 BCA ¶ 35,243 (Feb. 20, 2013) (substantial similarity
between FCA and claim warranted dismissal of Board case without prejudice) with ERKA
Construction Co., 12-2 BCA ¶ 35,129 (Aug. 16, 2012) (fraud issues readily distinguishable from
the issues in the Board case, case can go forward).
11
General Pricing Considerations (Cont.)
12
Pricing Methodologies
Elements of Cost Method
Direct Labor
Direct Materials
ODCs (e.g., Subcontractors, Travel, IT)
Overhead/G&A
Profit
FAR §15.404-4 Weighted Guidelines/Factors (Complexity, Risk, Capital Employed)
Contract Rate
Contract Exclusione.g., FAR 52.242-14, Suspension of Work
Contract Caps/Clauses
Actual Cost Method
Preferred Method
Requires Early Recognition/Establishment of Separate Job Cost Codes
Certain Entitlement Theories Present Difficulties (e.g., interference)
Establish Connection to Government Conduct
Cumulative Impact of Multiple Changes
Change Order Accounting Requirement
FAR § 52.243-6: For changes over $100,000, CO “may require change order accounting,which
requires the contractor to maintain separate accounts or otherwise segregate changes allocable to
the change. Applies “until the parties agree to an equitable adjustment for the charges…or the
matter is conclusively disposed of.”
Applies when CO issues change order and may apply to constructive changes. See, e.g., Svc. Engineering Co.,
ASBCA No. 40274, 93-1 BCA ¶ 25,520 (Oct. 13, 1992).
13
Pricing Methodologies (Cont.)
Estimated Cost Method
Claims/REAs Often Require Some Type of Estimate(s)
Actuals unavailable/lack of segregation
Future impacts
Methods Include:
Buildup through studies, use of Subject Matter Experts (SMEs)
Analogy/Actual cost of single event
Parametric/Cost Estimating Relationship (CER)—”top-down” [e.g., number of work-stations]
Weighted average3 or more similar projects
Engineering build-up
Keys:
Detail of analysis
Ability to tie directly to impact
Validity of any comparison
Experience/Training of personnel
14
Pricing Methodologies (Cont.)
15
Pricing Methodologies (Cont.)
Total Cost Method
Difference Between the Bid Cost/Price and Actual Cost
Disfavored, Because it Assumes the Entire Cost Overrun is the Government’s Fault
ElementsContractor Must Show:
The impracticability of proving its actual costs
The reasonableness of its bid
The reasonableness of its actual costs
A lack of responsibility for the added costs
Modified Total Cost Method
Total Cost Method
Adjusted for any Deficiencies in the Contractor’s Proof in Satisfying the Requirements of
the Total Cost Method
Jury Verdict
Least Favored
Requires clear proof of injury, no more reliable method for calculating damages, sufficient
evidence for a fair and reasonable approximation
Price Adjustment Should Equal the Amount of Cost the Contractor Would
Have Incurred Had the Work Been Performed (“Would-Have-Cost” Rule)
See, e.g., EJB Facilities Servs., ASBCA No. 57547, 13 BCA ¶ 35,399 (Aug. 28,
2013); Celesco Indust., Inc., ASBCA No. 22251, 79-1 B.C.A. ¶ 13,604 (Nov. 30,
1978).
If contractor is in a loss position, contractor must bear loss that it would
have incurred had the change not been issued.
See. e.g., Fox Constr. Inc., ASBCA No. 55265 et al., 08-1 BCA ¶ 33,810 (Mar.
5, 2008); S. N. Nielson Co. v. United States, 141 Ct. Cl. 793 (1958).
On the other hand, a contractor is permitted to show that it could have
performed the work for less than its original estimate entitled to retain
excess amount.
See, e.g., Dan G. Trawick III Contractors, ASBCA No. 47779, 98-2 BCA
29,781 (May 13, 1998); Admiral Corp., ASBCA No. 8634, 1964 B.C.A. ¶ 4161
(Mar. 24, 1964).
16
Pricing Deleted Work
Exception to “Would-Have-Cost” Rule: “Severable” Deletion:
Where separately priced item of work is deleted, adjustment measured by the
stated contract item price v. “would-have-cost”
Government Burden
Can deprive contractor of high profit it would have earned if it had performed
the deleted work; or save the contractor from the loss it would have incurred if it
had to perform the work
Key test: whether deleted work is actually severable from other line items, or
whether award was made on “aggregate” basis. See EJB Facilities Servs.,
ASBCA No. 57547 (2013)
17
Pricing Deleted Work (Cont.)
Contractor entitled to overhead and profit as part of an equitable
adjustment that increases performance costs
May be limited by contract terms
Conversely, government can reduce overhead and profit amounts on changes
that delete work
18
Overhead and Profit
For changed work with minor cost increases, use of ordinary overhead
rates may be appropriate
For changed work with significant cost increases, parties may negotiate
specific overhead rates/costs
Treatment of overhead costs for changed work must not violate contractors
established accounting practices
E.g., Contractor cannot treat site overhead as both a time cost and as a percentage add-on cost.
M.A. Mortenson Co., ASBCA No. 40750, 98-1 B.C.A. ¶ 29,658.
19
Overhead
Contractor entitled to fair profit for changed work.
Even if contractor was not going to recover profit on the unchanged work (see e.g.,
Stewart & Stevenson Srvs, Inc., ASBCA No. 43631, 97-2 B.C.A. 29,252 (Sept. 23,
1997))
Contractor generally required to reduce profit relating to changes that reduce
costs (see e.g., Keco Indust., Inc., ASBCA No. 15131, 72-1 B.C.A. ¶ 9,262 (Dec.
3, 1971))
If, however, the contractor is not earning any profit, there is no requirement to reduce
profit related to deleted work (see e.g., States Roofing Corp., ASBCA No. 55507, 09-1
B.C.A. ¶ 34,094 (Mar. 4, 2009))
Amount of profit to be added or deducted as part of equitable adjustment is a
matter of negotiation
For minor changed work, contracting parties can use profit rate in original contract (or
other reasonable amount)
For major changed work, parties negotiate profit based on weighted factors (FAR §
15.404-4(b)(1)-(d); DFARS §§ 215.404-4(b), 215.404-71-1): work complexity, effort,
contractor risk, etc.
Profit for changed work may be limited by special contract clauses/caps
20
Profit
21
Changes
Government Delay v. Concurrent Delay (e.g., FAR § 52.242-17)
Excusable Delay v. Compensable Delay (e.g., FAR § 52.249-8)
Excusable Delays (e.g., FAR 52.249-8): Acts of God, Acts of Government in Sovereign or Contractual Capacity,
Fires, Floods, Epidemics, Strike, Unusually Severe Weather
Beyond Control and Without Fault of Contractor
Subcontractors: (1) Without Sub Fault; (2) No Other Source
Cost Elements: Idle Labor and Equipment, Rental Equipment, Loss of Efficiency
(“Measured Mile”), Escalation of Labor Costs; Performance in Later/ Costlier Time
Period, Other (e.g., Storage, Additional Bond Premium Amounts)
Acceleration:
Contractor Effort to Make Up for Excusable Delays
Cost Elements: Excess Labor, Overtime Premiums, Material Cost (expediting), Adverse
Conditions, Loss of Efficiency
Impact on Other Work
Profit Generally Not Permitted
Special SituationsPricing Delays
22
Special SituationsPricing Delays (Cont.)
Unabsorbed OverheadEichleay Corp., ASBCA No. 5183, 60-2 BCA
2688 (July 29, 1960):
Three Conditions:
Government-caused delay
Contractor was on “Standby” (Delay=Uncertain, Indefinite Duration)
Accordingly, if actual overhead is allocable to the project, then Eichleay is inapplicable. See Shirley Contracting
Corp., ASBCA No. 29848, 1984 WL 582414 (Dec. 27, 1984); Excavation-Construction, Inc., ENGBCA No. 3858,
82-1 BCA ¶ 15,770 (Apr. 30, 1982).
Contractor could not have taken on additional work
Calculation Method:
(Total Contract Billings / Total Company Billings) x Total Home Office Overhead During Contract =
Overhead Allocable to the Contract
(Allocable Overhead / Days of Contract Performance) = Daily Contract Overhead
Daily Contract Overhead x Number of Days of Delay = Unabsorbed Overhead
Still commonly used formula.
Nicon, Inc. v. United States, 331 F.3d 878, 888 (Fed. Cir. 2003); Tulsa Mid-W. Constr. Co., ASBCA
No. 55173, 07-2 BCA ¶ 33,646 (Aug. 2, 2007).
Subs Typically Cannot File Claims Directly with the GovernmentNo
Privity of Contract
Prime must “Sponsor” sub claims to Government and there must be “line of
privitybetween the subcontractor and the government
Severin v. United States, 99 Ct. Cl. 435 (1943) (Prime cannot sue Government on behalf of a
sub unless the Prime is itself liable to the sub)
Any Sub Claim Exceeding $100K Must Include Proper CDA Certification
Language from 41 U.S.C.§ 7103(b)(1)
Sub REAs arising from DoD Contracts must include DFARS § 252.243-7002
certification language
Prime should reject any deviations to certification language in sub claims/REAs
Prime Certification of sub claims can be based on “Good Grounds,” see
Transamerica Ins. Corp. for and on behalf of Sharp Sheet Metal Works v.
United States, 973 F.2d 1572 (Fed. Cir. 1992), overruled on other grounds by
Reflectone v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995).
23
Special SituationsSubcontractor Claims
Apply Prime’s Overhead and Profit to Sub Claims
Understand and Vet Sub’s Claim/REA Pricing Method
Pricing methodology
Factual support
Flow-down audit clauses to facilitate Prime’s review of sub’s financial data
Obtain, Review, and Submit Sub Cost or Pricing Data if the REA Exceeds the
TINA Threshold ($750,000) if applicable
Non-commercial
Will result in modification
Agreement on price
Obtain Sub’s Agreement to be Bound to Result of Final Amount Determined Due
under Claim
24
Special SituationsSubcontractor Claims (Cont.)
DMS Imaging, Inc. v. United States, 123 Fed. Cl. 645 (2015)
Government liable for MRI machine leased after it was destroyed in a fire.
Cost elements:
Fair market value of machine
Lease payments due after destruction of equipment
Contractual late fees and service fees
Attorney’s fees
CDA interest
SUFI Network Servs., Inc. v. United States, __ Fed. Cl. __, 2015 WL 7954529
(2015).
COFC denied the contractor's claims for overhead and profit on the attorneys' fees previously awarded because there
was no contractual basis for the recovery.
Contractor equitably estopped from changing the method used to calculate its attorneys' fees from the traditional
lodestar method to an approach based on the amount it was required to pay the law firm under the contingent fee
agreement.
Though not technically a CDA case, “the parties likely would accept such a result as being typical in federal
procurement law.”
May be persuasive in future cases.
25
Recent Developments
26
Best Practices
Be Proactive/Start Early
Cross-function Cooperation and Communication (Legal/Contract/Pricing)
Identify Potential Changes and Initiate Segregation of Increased Costs
Immediately
Assign separate cost accounting number
Contract may require change order accounting (FAR § 52.243-6)
Document Estimates in Sufficient Detail and Verify Bases of Estimate
Delays: Regularly Update Schedule to Reflect Changes as They Occur
Cost Allowability: Clearly Draw Lines between Negotiations and Contract
Administration and Certified Claims
Manage/Avoid Broad Release Language (“known or unknown”) May Have
Unintended Consequences
Preserve Delays, Cumulative Impact
27
Best Practices (Cont.)
Scrub Carefully for Unallowables
Anticipate DCAA Challenges to Estimates:
Relevance/Causation/Reliability of Increased Costs Data
Unallowables
Reasonableness of Labor Hours
Attorney/Accountant Fees
Profit
Interest on Claim
Questions?
Steven M. Masiello
Partner
Government Contracts
303.634.4355
Joel M. Pratt
Associate
Government Contracts
303.634.4324
28
Thank you
Dentons US LLP
1400 Wewatta Street
Suite 700
Denver, CO 80202-5548
United States
Dentons is the world's first polycentric global law firm. A top 20 firm on the Acritas 2015 Global Elite Brand
Index, the Firm is committed to challenging the status quo in delivering consistent and uncompromising
quality and value in new and inventive ways. Driven to provide clients a competitive edge, and connected
to the communities where its clients want to do business, Dentons knows that understanding local cultures
is crucial to successfully completing a deal, resolving a dispute or solving a business challenge. Now the
world's largest law firm, Dentons' global team builds agile, tailored solutions to meet the local, national and
global needs of private and public clients of any size in more than 125 locations serving 50-plus countries.
www.dentons.com.
© 2015 Dentons. Dentons is a global legal practice providing client services worldwide through its member firms and affiliates. This publication is not designed to provide legal advice and you should not take, or refrain from taking,
action based on its content. Please see dentons.com for Legal Notices.
29