• Contractor entitled to fair profit for changed work.
• Even if contractor was not going to recover profit on the unchanged work (see e.g.,
Stewart & Stevenson Srvs, Inc., ASBCA No. 43631, 97-2 B.C.A. ¶ 29,252 (Sept. 23,
1997))
• Contractor generally required to reduce profit relating to changes that reduce
costs (see e.g., Keco Indust., Inc., ASBCA No. 15131, 72-1 B.C.A. ¶ 9,262 (Dec.
3, 1971))
• If, however, the contractor is not earning any profit, there is no requirement to reduce
profit related to deleted work (see e.g., States Roofing Corp., ASBCA No. 55507, 09-1
B.C.A. ¶ 34,094 (Mar. 4, 2009))
• Amount of profit to be added or deducted as part of equitable adjustment is a
matter of negotiation
• For minor changed work, contracting parties can use profit rate in original contract (or
other reasonable amount)
• For major changed work, parties negotiate profit based on weighted factors (FAR §
15.404-4(b)(1)-(d); DFARS §§ 215.404-4(b), 215.404-71-1): work complexity, effort,
contractor risk, etc.
• Profit for changed work may be limited by special contract clauses/caps
20
Profit