Publication No. EF18-14025 revised 01/23/13
A phased project classification can be added to the type of work; it cannot be marked alone. (The project may be a
phased renovation or a phased demolition - the phased box AND either the renovation box or demolition box must be
checked). A description of the phased project schedule must be sent to the appropriate DSHS or Local Program
inspector. The DSHS policy regarding phased projects must be strictly followed, if that box is checked. (A copy of the
phased project policy letter can be obtained by calling any DSHS inspector). The scheduled work time must be
checked. A description of the work schedule must be provided, if the schedule varies from that listed as the project
dates (Section 16 and/or Section 17). Example: If a project is scheduled to last one month, but the contractor will not
be working on the weekends, a statement should be included that say “Working Monday - Friday.” The statement must
be accurate; an inspection will be based upon the provided information.
III) Provide the name of the building or an identifying description. Example: vacant warehouse. A physical address must
be provided (not a post office box) and a sufficient description must be provided to locate the site in the event that the
address alone is inadequate. The ZIP CODE for the building MUST be provided. The name of a contact person at the
facility MUST be provided for inspection purposes, even if the building or facility is vacant. If the building does not
have a phone, list the contact person’s phone number.
The type of building/facility must be checked. Only one box may be checked. An example of a NESHAP-Only
Facility would be a house that was being demolished as part of a Texas Department of Transportation right-of-way
project, or a ship.
Detailed information must be provided in all spaces, including the age and size of the building or facility. Check
whether the building/facility is occupied. If the building/facility is vacant during the time of the renovation, but will
later be re-occupied (not demolished), then indicate that the building/facility is occupied.
An asbestos survey/inspection must be performed prior to any renovation or demolition. A DSHS licensed inspector
must perform the inspection if the project is in a public building. Provide the DSHS Inspector License Number, if
required. If the survey/inspection was performed in a public building prior to January 1993, or if the project is not in a
public building, "N.A." should be placed in the space for the DSHS License Number. The date that the survey was
performed must be provided. The analytical method used to detect the presence of asbestos must be checked. TAHPR
requires that a DSHS licensed laboratory perform the analysis of samples from public buildings. Provide the DSHS
Laboratory Number if the samples are collected from a public building. The assumption of asbestos-containing
building material (for renovations) in a public building must be made by a DSHS licensed inspector. The date that the
survey (assessment) was performed would be provided, the DSHS Inspector License Number would be provided, and
the “assumed” analytical method box would be checked on the notification form, for an assumption of any asbestos-
containing materials that would be abated during a renovation project. When an assumption of asbestos-containing
material is done in a non-public building, all of the above must be completed except for the DSHS Inspector and
Laboratory License Numbers (not required). If there was no suspect material discovered, such as a garage, built of
concrete and steel only, indicate that no suspect material was found.
IV) If ACBM is to be removed before a building is to be demolished or renovated, enter the removal dates (start and
completion) in this section. Asbestos abatement work includes any activity which will disturb ACBM. The asbestos
abatement start date is the date that asbestos will be disturbed. The asbestos abatement activity stop date is the date
upon which air monitoring clearance has been achieved. In no event shall an abatement start or be completed on a
date other than the dates entered in this section (see Section 295.61(f)). Refer to Section I for information on
notifying of any change in the start and completion dates.
Enter the scheduled dates for the start and completion of the building demolition. In no event shall a demolition start
or be completed on a date other than the dates entered in this section. Refer to Section I for information on
notifying of any changes in the start or completion dates. When the building will not be demolished, but an abatement
will be performed, the dates of the total renovation (remodeling) project can be provided in this section. The
notification will remain active, if the renovation dates are provided.
V) If asbestos is present, the chart must be completed. If no asbestos is present (as revealed by the survey), check the box
provided. Category I non-friable ACBM includes floor tile, when removed intact, floor tile mastic, gaskets, and roofing
material. Category II non-friable ACBM includes transite siding. Use the appropriate row to designate whether the
“Category I or Category II non-friable ACBM removed” is located on the interior or exterior of the building. If
Category I or II materials are to be sanded, ground, abraded, crumbled, pulverized, reduced to powder, or have the