SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.1
SUBMISSION GUIDE FOR ARCHITECTS
CONTENTS
TAB 5 REQUIREMENTS DURING CONSTRUCTION
(The Pre-Construction Meeting Guide)
Page
CONTENTS ................................................................................................................... 5.1
5.01 PHFA Requirements During Construction .................................................................... 5.2
5.02 Procedures Change Orders (Appendix 1) ................................................................ 5.10
5.03 PHFA Change Order Log (Appendix 2) ...................................................................... 5.13
5.04 Change Order Form C5 (Appendix 3) ......................................................................... 5.15
5.05 Procedures Occupancy (Appendix 4) ...................................................................... 5.17
5.06 Punch List Form (Appendix 5) ..................................................................................... 5.18
5.07 PHFA Certificate of Substantial Completion (Appendix 6) .......................................... 5.19
5.08 Certificate of Occupancy (Appendix 7) ........................................................................ 5.21
5.09 Procedures - Final Inspection/Construction Completion (Appendix 8) ....................... 5.22
5.10 PHFA Final Inspection (Appendix 9) ........................................................................... 5.23
5.11 Certificate of Construction Completion (Appendix 10) ................................................ 5.24
5.12 Procedures - Construction Payouts (Appendix 11) ..................................................... 5.25
5.13 Contractor Payment Form, Application and Certificate for Payment
AIA Document G702 (Appendix 12) and AIA Document G703 (Appendix 13)
[not bound in manual] .................................................................................................. 5.26
5.14 PHFA Rental Housing Program, General Contractor’s Actual
Construction Cost Certification (Appendix 14) ............................................................ 5.27
5.15 Contractor’s Certification of Compliance with Design
Requirements for Accessible Housing (Appendix 15) ................................................. 5.28
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.2
SECTION 5.01
PHFA REQUIREMENTS DURING CONSTRUCTION
(The Pre-Construction Meeting Guide)
The purpose of this section is to outline the basic responsibilities and duties of the various parties
throughout the construction period. This section was made part of the construction documents as defined
in Article 1, Item 1.1, of the Supplementary General Conditions and Article 1, Item B, of the PHFA
Addendum to the AIA documents. It is understood by the Pennsylvania Housing Finance Agency (PHFA)
that circumstances may vary from development to development depending on the size, scope and
financing arrangements. PHFA will consider changes or variations of this section as circumstances
warrant.
5.01.1. DUTIES AND RESPONSIBILITIES
A. Contractor:
The Contractor will provide the following items at the construction site:
1. Temporary Office Space:
Office for use by PHFA’s Technical Services Representatives, which must be
equipped or have access to the following amenities:
a. Access to telephone
b. Lockable file cabinet
The space should be adequately heated and air conditioned and provide a decent
working environment throughout the construction period.
2. Construction Sign:
PHFA will provide a sign to be immediately displayed in a prominent location
approved by PHFA. This sign must be returned to PHFA at construction
completion.
3. Photographs:
a. New Construction:
The Contractor shall have six (6) views of the site taken each month.
Photographs shall show the progress of the work and shall be 8” x 10”
glossy prints. Two copies of all prints shall be submitted to the Technical
Services Representative. Prints shall bear the date of exposure,
development name, number and the location of the photograph.
Commencing with the interior partitioning, four of the six views shall be of the
interior. The views shall be generally taken from the same locations to
indicate the Contractor’s progress in the construction of the development.
b. Rehabilitation/Preservation:
The Contractor shall have six (6) 8” x 10” photographs of the development
taken each month and submitted to PHFA’s Technical Services
Representative. The photographs should be arranged so that a before and
after sequence is developed for major components such as windows,
roofing, bathrooms, kitchens, mechanical equipment and site work.
b. Eleven (11) Units or less:
Number and type of photographs may be determined by the Technical
Services Representative.
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.3
c. These photographs shall be submitted to the Architect monthly at the payout
meeting.
5.01.2. PROGRESS MEETINGS
A. Architect:
The Architect must monitor the progress of construction for conformance to Contract
Documents and the Construction Progress Schedule.
B. Contractor:
Within ten days after award of the construction contract, the Contractor shall, in a form
approved by PHFA, furnish the Architect, PHFA and PHFA’s Technical Services
Representative a construction schedule showing the work to be performed and the time
of completion of each specified section of work. The chart shall be updated and
presented at each payout meeting, or as directed by the Architect or PHFA. Revisions to
the schedule shall not be in effect until approved by the Owner, Architect and PHFA.
5.01.3. MEETINGS
A. Architect:
1. The Architect will conduct job meetings a minimum of once every two weeks with
Representatives of the Owner, PHFA, Contractors, Subcontractors and Local
Authorities. A portion of the meeting will be reserved for an on-site observation
of the development to determine conformance of work, materials and
equipment to the Contract Documents. Minutes of these meetings shall be sent to
all those in attendance (and a copy to the Technical Services Representative if
absent from the meeting). The Architect or Architect’s representative should be
available to attend any additional meetings requested by PHFA or the Owner.
2. The Technical Services Representative may perform site observation of the
contract work during weeks not having a scheduled job meeting. The Technical
Services Representative will inform the Architect of any observed deficiencies in
the contract work or other concerns that may result from this “off week” visit. All
such deficiencies and concerns must be discussed at, and made part of the
minutes of, the next job meeting. The Architect will be responsible for any and all
directive action required to satisfactorily address and resolve these deficiencies or
concerns. If it is the opinion of the Technical Services Representative that the
observed deficiency or concern during this “off week” is critical, the Architect must
initiate corrective measures immediately (that same day).
B. Contractor:
The Contractor will attend all meetings and will encourage all Subcontractors to attend
during the critical portion of their work.
5.01.4. SHOP DRAWINGS AND FIELD DOCUMENTS
A. Architect:
The Architect will review shop drawings, catalog cuts and other field documents
approved by the Design Architect and make minor revisions or notations required by field
conditions. Mail or hand deliver, to the attention of the assigned Technical Services
Representative in the appropriate PHFA office, one copy of the approved shop drawings
and all test reports, and two copies of the following field documents:
1. Job conference reports
2. Photographs
3. Progress schedule
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.4
B. Contractor:
The Contractor shall submit to the Architect all shop drawings and catalog cuts in
sufficient time to allow the Architect for review. The actual number of required copies
shall be determined by the Architect.
5.01.5. TESTING
A. Architect:
The Architect will make certain that tests required by specifications, all applicable
regulatory entities and as detailed in PHFA’s Submission Guide for Architects are being
properly performed by qualified personnel, evaluate results and recommend action in the
event of unsatisfactory results.
B. Contractor:
The Contractor, unless the Owner is designated in writing as responsible, shall be
responsible and pay for all tests required by the Architect, all applicable regulatory
entities and PHFA. Copies of the results of all tests shall be furnished to the Owner,
Architect and PHFA’s Technical Services Representative. The testing laboratory must
be approved by the Architect.
5.01.6. CHANGE ORDERS (See Appendices 1, 2 and 3)
A. Contractor:
1. If a Contractor determines that items of work not covered in the Contract
Documents must be done, a request will be made by the Contractor to the
Architect within fifteen working days after discovery. If a request for a Change
Order is not submitted within this time, the changes may be disapproved by PHFA.
2. Independent/unrelated credit change orders must be submitted on separate forms.
The exception being a credit given to accommodate newly added change order
work (i.e., a credit for vinyl tile and an add of carpet at the same area may be on
the same change order request; but a credit for deleted landscaping and an add
for window treatment must be on separate change order forms).
3. Multiple independent credit change orders may be submitted on one form.
4. Except for work of an emergency nature, all proposed changes in the scope of
contract work must be discussed during the job meetings prior to that work
commencing. All such changes in work scope must be agreed to by the Owner,
Architect, Contractor and PHFA.
5. The Contractor will submit the CHANGE ORDER FORM C5 to the Architect with
adequate substantiation as outlined in Appendix 1.
B. Owner:
1. The Owner, with written approval of PHFA, may request extra work or request
changes by altering, adding or deducting from the contract work. All such changes
will be processed in accordance with PHFA’s change order procedures. If the
change order is an “add” and the contingency has been expended, a check in the
amount of the change order must be attached to the change order request.
2. PHFA reserves the right to require the Owner to fund from sources other than the
contract contingency account, any/all change orders for the provision of work
which may have been previously removed from the contract via Addendum, value
engineering or similar agreements. This stipulation is true regardless of the
contingency account balance.
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.5
3. PHFA reserves the right to require the Owner to fund from sources other than the
contract contingency account any/all change orders for provision of work, for fees,
for permits, for design costs or similar required to satisfy utility providers and/or
Governing Municipalities. Design and/or review fees associated with additional
utility work, hook-up fees, service extensions, etc., also fall under this stipulation.
This stipulation is true regardless of the contingency account balance.
4. These change orders must be submitted within fifteen working days after it has
been determined that the work is required. Any change orders submitted after this
time frame may not be approved by PHFA.
C. Architect:
1. Upon receipt of a request for a change order and after review as indicated in the
change order procedures, the Architect will forward his/her recommendations to
the Owner, together with all proper substantiation. The recommendations shall be
in written form and refer to the Contract Documents defining where and why the
change is warranted.
2. The Architect will forward this information to the Owner within fifteen days after it is
received from the Contractor. Any change orders not forwarded within this fifteen
day limit may be disapproved by PHFA.
5.01.7. PROCEDURES OCCUPANCY / SUBSTANTIAL COMPLETION (See Appendices 4, 5, 6, 7
and 15)
A. Contractor:
The General Contractor is responsible for compiling an initial punch list for all areas of
the building(s). Along with the Architect, Technical Services Representative and at
his/her option, the Owner, the General Contractor will perform a punch list inspection on
each typical space type within the facility in order to set an acceptable standard of what
the finished product is to be. Based on that standard, the General Contractor will
perform similar inspections of the work as a whole. The General Contractor will prepare
a punch list of that inspection indicating the location, date, inspector’s name and nature
of deficiency. A copy of that initial punch list must be submitted to the Owner, Architect
and the Technical Services Representative.
B. Architect:
At a time when the General Contractor indicates that all initial punch list items have been
addressed as to comply with the acceptable standards, the Architect, together with the
Technical Services Representative and General Contractor, will conduct an inspection of
the building(s) and units to be occupied to verify that all corrective work is satisfactorily
completed and that there are no other apparent deficiencies not on the initial punch list.
Should a pattern of nonconformance to the acceptable standard be observed, this
inspection can be terminated until such time that the work is satisfactory.
Use Appendix 5 as a reference guide when performing punch list inspections, however,
the format on Appendix 5 is not mandatory. During this inspection the Contractor will
confirm that the development has been constructed according to the drawings and
specifications as they pertain to design requirements for accessible housing and
complete two copies of Appendix 15, “Contractor’s Certification of Compliance with
Design Requirements for Accessible Housing,” to submit to the Architect. Appendix 15
must be fully executed in order for PHFA to issue a Certificate of Occupancy. The
Architect will submit the punch list to the Contractor and the Technical Services
Representative. After the punch list items have been completed by the Contractor,
PHFA’s Technical Services Representative, the Architect, the Contractor and all other
funding parties having a vested interest will re-inspect the buildings.
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.6
If upon re-inspection of the building(s), it is unanimously determined that all significant
punch list work is satisfactorily completed, the Architect will prepare and submit the
“Certificate of Substantial Completion” to the Technical Services Representative
accompanied by the fully executed Appendix 15 form.
C. Owner:
PHFA will issue a Certificate of Occupancy (see Appendix 7) to the Owner provided all
occupancy permits and/or building code inspections have been issued and/or performed
by all Local Regulatory bodies, all areas having been punch listed have been re-
inspected and all significant deficiencies/work is satisfactorily completed and Appendix
15 has been fully executed. The Owner shall not schedule any move-ins until all
aforementioned criteria have been met.
D. Contractor:
The Construction Superintendent or a representative must accompany the Architect and
PHFA’s Technical Services Representative on their Substantial Completion Inspection.
Upon receiving the punch list from the Architect, the Contractor must complete the
necessary corrective work within fifteen (15) days and notify the Architect that the punch
list items are complete. Re-inspection will not occur until all significant punch list items
have been rectified. Minor cosmetic and/or seasonal dependent punch list items may, at
PHFA’s discrepancy, be carried over without affecting issuance of the certificate of
occupancy.
5.01.8. FINAL INSPECTION (See Appendices 8, 9 and 10)
A. Architect:
1. The Final Inspection will be conducted by the Architect with Representatives of
PHFA, Owner and Contractor.
2. The final inspection must cover all interior and exterior systems including those
minor items from the initial punch list which have not been completed or corrected
and items awaiting seasonal opportunity.
3. After completion of the final inspection, the observing Architect will submit the final
inspection form and final/remaining punch list to those attending the inspection for
their signature indicating agreement with the items listed and proposed correction.
Two completed copies must be given to the Technical Services Representative.
4. If the above form is in compliance with the procedures as stated, PHFA will issue a
Certificate of Construction Completion specifying the “Date of Actual Construction
Completion” to the Owner.
B. Owner:
The Owner may authorize the Architect to be their representative at the final inspection.
Upon issuance of the Certificate of Construction Completion, PHFA’s Finance Division
will establish the cost certification cut-off date.
C. Contractor:
After completion of the final remaining seasonal punch list items, the Contractor must
notify the Technical Services Representative and all other responsible parties and
schedule and perform a re-inspection.
5.01.9. WARRANTIES / GUARANTEES AND MATERIAL TAKE-OFFS
A. At 75% completion, the Architect must send the General Contractor a list of the
Warranties/Guarantees required under the specifications. One copy of each
warranty/guarantee must be submitted to the Technical Services Representative prior to
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.7
construction completion. This submission shall also include a list of all major
Subcontractor and material suppliers, including name, trade, address and phone
number. The originals should be forwarded to the Architect. Final Closing cannot be
scheduled until all warranties/guarantees and material take-offs are received.
B. At the four month guarantee inspection, PHFA will provide the Contractor a list of
building materials that will be used to compile the PHFA Reserve for Replacement
Spreadsheet. The Contractor is required to provide material quantities for each item on
that list no later than the time of the eleven month guarantee inspection. Failure of the
Contractor to comply will result in the delay of denial to the release of final retention in
the same vein of failure to comply with submission of warranty and guarantee
information.
5.01.10. GUARANTEE PERIOD
A. Architect:
1. During the One year Guarantee Period, the Architect is required to inspect the
development three times, at the four, eight and eleven-month date intervals. If the
development was granted phased substantial completions by the Architect that
Architect is then required to perform the same three guarantee inspections for
each of these phases at the same intervals. The Architect is to coordinate and
notify the Contractor, Technical Services Representative and Owner of the dates
and times of these inspections. A report of each inspection will be forwarded to
PHFA promptly. Representatives from PHFA will be available to accompany the
Architect on these guarantee inspections.
2. The Architect on the development will have 2 ½% of their fee (but not less than
$1,600) of the supervision fee retained at the final payout stages of the
construction period to cover the cost of all the inspections required during the one-
year guarantee period.
3. If the Architect has fully performed his duties under the contract related to the
guarantee period, the retained fee will be released as follows:
a. After satisfactorily fulfilling the first guarantee inspection criteria, an amount
equal to 25% of the total retainage will be released.
b. After satisfactorily fulfilling the second guarantee inspection criteria, an
additional amount equal to 25% of the total retainage will be released.
c. After satisfactorily fulfilling prior guarantee inspection criteria and the third
guarantee inspection criteria, the balance of or total retainage will be
released.
B. Owner:
1. The Owner shall ensure that a Representative of the Management Firm attends
each Guarantee Inspection.
C. Contractor:
1. The Contractor will correct any latent defects due to faulty materials or
workmanship which appear during the One-year Guarantee Period. In case the
Contractor fails to correct the defects, the Owner with consent of PHFA may
furnish the materials and/or labor deemed necessary to correct the defects, with all
associated costs being back-charged against the Contractor.
2. If the Contractor is not represented at the quarterly meeting, it will be his/her
responsibility to correct all items described by the Architect as Contractor related.
5.01.11. DEVELOPMENTS WITH 11 UNITS OR LESS
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.8
Developments with 11 units or less may have two Guarantee Inspections at six-month
intervals. The Architect’s retention of 2-½% of their fee (but not less than $1,600) will be
reduced by 50% at the six month guarantee inspection, and final payment will be made after
the twelve month inspection if items are complete. Release of retention is contingent upon the
Architect fully performing his duties under the contract.
5.01.12. GUARANTEE INSPECTION PROTOCOL
A. The Architect is required to attend all Guarantee Inspections. The Contractor is strongly
encouraged to attend all guarantee inspections.
B. At all four and eight month guarantee inspections, all common areas, exterior and any
other spaces, locations or systems that are noted by site management/maintenance staff
as having been experiencing problems must be observed by all participants. The
Architect shall be responsible for the compilation and distribution of the notes, minutes,
observed deficiencies list, etc., associated with the four and eight month guarantee
inspections. All such documents must be sent to all parties having been in attendance,
as well as any and all other parties which may have an interest in the work (i.e.,
investors, consultants, etc.).
C. At the eleven month guarantee inspection, all contract work areas which include 100% of
the dwelling units must be observed by all participants. The Architect shall be
responsible for the compilation of any and all observed deficiencies that are directly
attributable to the work that the Contractor was obligated to perform. The Architect shall
send this list to PHFA. If requested, the Architect may provide a copy of this list to the
Owner and/or Contractor. PHFA will be responsible for the compilation of any and all
observed deficiencies that are directly attributable to management and/or maintenance
practices at the property. PHFA will send its list as well as the Contractor related list
having been compiled by the Architect to the Owner. The Owner shall be responsible to
assure that all items on all lists are adequately and satisfactorily addressed. The Owner
must also send monthly, written updates to PHFA informing PHFA of the progress being
made on the work required to satisfy the deficiencies on both lists.
5.01.13. RECORD DRAWINGS
A. Architect:
Record Drawings (As-Builts) shall be prepared by the Design Architect from a set
maintained on the job by the General Contractor. One complete electronic set (PDF on
CD) set shall be submitted to PHFA. One complete hard copy set shall be submitted to
the Owner. The remaining portion of the retention will be released after review and
approval of the drawings. The Architect shall review the Contractor’s marked-up field
record set for accuracy at each weekly payout meeting.
B. Contractor:
The Contractor must maintain a set of marked-up Record Drawings at the site, including
site, architectural, structural, plumbing, HVAC, electrical, fire protection, etc., which will
be released to the Design Architect upon completion of construction for the preparation
of the Record Drawings.
5.01.14. CONSTRUCTION PAYOUTS (See Appendices 11, 12, 13 and 14)
A. Contractor:
1. A Payout Field Work Sheet will be supplied by PHFA prior to or between each
payout meeting.
2. The Contractor must fill in the field work sheet indicating the amounts due for each
line item.
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.9
3. After a walk through and the amounts are confirmed, the sheet will be signed by
the Representatives of the Contractor, PHFA and Architect, and a copy will be
given to the Technical Services Representative. The General Contractor must
promptly prepare three copies of the AIA Form G702, “Application and Certificate
for Payment,” and forward same to the Architect.
4. Any/all questions concerning the status of previously approved payment
applications shall be directed only to the Technical Services Representative.
B. Architect:
1. The Architect will review the quantities requested and will initial the Technical
Services Representative’s Field Work Sheet on the field cut-off date. Upon receipt
of Form G702 from the Contractor, the Architect will sign and forward it to the
Owner.
2. The Architect will also forward his/her monthly requisition to the Owner for
inspection. The amount allowed is based upon the percentage of construction
completion and should not exceed that percentage.
C. Owner:
Upon receiving the Construction Payout from the Architect, the Owner will review the
payout, attach a P-2 requesting non-construction items and forward it to PHFA’s Finance
Division for processing. The Owner shall also call their bonding agent to adjust the value
of the development by the amount of the payout and request a bring-down which is
required by PHFA prior to any release of funds.
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.10
SECTION 5.02
PROCEDURES CHANGE ORDERS
5.02.1. GENERAL
A. The Owner, Architect or Contractor may request a Change Order to cover additions,
deletions or upgrades to the Contract Documents.
1. When it becomes necessary to make any of the above modifications to the
contract, a change order shall be prepared and submitted to PHFA for approval
within fifteen (15) business days after it has been determined that the work is
required. Changes not processed within this time frame may be disapproved by
PHFA, regardless of funding source. All such changes are subject to conditions
set forth in this Guide and will be processed as described herein.
2. Cost or credit for the work proposed by change orders will be determined in
accordance with the General Conditions AIA Document A201 and related PHFA
SUPPLEMENTAL GENERAL CONDITIONS.
3. After the Contractor has compiled his/her own construction costs for the change
order work as well as the construction costs of any and all Subcontractors, and a
total dollar value for the work has been determined, the Contractor will be allowed
to add the following to the cost:
a. Builder’s Overhead (defined as the expenses necessary to the operation of a
construction business) and limited to 2% of the dollar value of the work.
b. Builder’s Profit limited to 6% of the dollar value of the work.
c. Any additional Bond Premium incurred as a result of the change order work.
4. When work is deleted, the Contractor shall submit a change order for the full value
of the deletion. When an approved item of lesser quality is installed, a change
order shall be submitted for the difference between the cost of the original item and
the lesser substitution.
B. Except under emergency conditions, no changes in contract work shall be made without a
change order signed by the Owner and PHFA. Work may be authorized on a time and
material basis, but the procedure for obtaining formal change orders remains the same.
Owners will contact the Technical Services Representative on emergency conditions and
verify emergency prior to the Contractor starting work on the change order.
C. Sufficient copies of letters, proposals and change orders must be prepared so that each
signatory has sufficient copies to process. Six original PHFA Change Order Forms C5
are required for submission to PHFA. Only two complete copies of all change order
substantiation documentation need be submitted.
D. When a development is thirty (30) days behind the original schedule, a change order must
be submitted to the Architect by the Contractor requesting a 30-day extension of time,
with all necessary documentation justifying the request.
5.02.2. PROCEDURES
A. Following the request for a change in the work, the Architect shall address a letter to the
Contractor (with copies to the Owner and PHFA) including the following information and
requesting a change order from the Contractor:
1. Nature and extent of work added, deleted or changed.
2. Supplementary drawings as required.
3. APPENDIX 1, Page 1 of 3
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.11
4. Reason for change.
5. Should the Contractor discover a necessity for a change or substitution, he shall
first call the Architect and obtain approval to proceed with the change order form.
B. The Contractor shall prepare and submit the final PHFA Change Order Form C5 to the
Architect indicating the following:
1. Nature and extent of work added, deleted or changed.
2. Supplementary drawings, specifications and other pertinent documentation.
3. Reason for change.
4. Detailed cost breakdown (labor and materials, supporting invoices) or lump sum as
required by Contract Documents).
5. The effect the change order will have on the construction schedule indicated as the
number of additional or fewer days required to complete the contract work.
C. The Architect, upon receipt of the Contractor’s change order, and after review as
indicated below, shall forward his recommendations to the Owner, together with all
proper documentation. The observing Architect, when applicable, shall:
1. Review the change for technical correctness and comment.
2. Review the change for reasonable cost.
3. Include a statement explaining why the modification to Contract Documents was
required.
4. Recommend acceptance, rejection, cost revisions or alternate solutions. Sign the
change order and forward it to the Owner.
D. The Owner will review the change order and suggestions received from the Architect and
accept or reject it. If accepted, the change order shall be signed by the Owner,
Contractor, Bonding Company, PHFA Technical Services Representative and other
required governing agencies.
In order to expedite processing of change orders, the Contractor may secure
documentations from their bonding company at the start of the contract work indicating
the bonding company’s intent and dollar value limit to which they will provide coverage.
Such documentation must be on official bonding company letterhead and must bear the
seal of that bonding company along with appropriate signature(s). A copy of such
document may be affixed to each change order request in lieu of the bonding company’s
individual approvals/signatures.
If the contingency fund is exhausted or if PHFA requests owner funding, the Owner shall
attach a check to the change order in a sufficient amount to cover the cost.
E. Upon receipt of the data in “D” (above) and the check from the Owner, PHFA shall:
1. Review the entire package.
2. Accept, reject or suggest modifications.
3. Authorize payment when included in the Contractor’s regular requisition.
4. Execute and return three copies of the change order to the Owner.
APPENDIX 1, Page 2 of 3
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.12
F. Change Order Log - At the first inference that a change is eminent, it shall be numbered
and recorded on the Change Order Log with an estimated cost.
When changes are approved, they shall be renumbered and entered on the approved
side of the log.
This log is the responsibility of the Architect and shall be updated and submitted to the
Technical Services Representative at each payout meeting.
APPENDIX 1, Page 3 of 3
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION
SECTION 5.03
PENNSYLVANIA HOUSING FINANCE AGENCY
CHANGE ORDER LOG
Development: ____________________________________________ PHFA No.: ___________
Sheet No.: __________
CONTRACTOR
APPROVED BY PHFA
REQUEST
FOR C.O. NO.
SUBMITTED
BY
DATE
VALUE
DESCRIPTION
C.O.
NO.
DATE
VALUE
REMARKS
EST.
TIME
EXT.
APPENDIX 2
5.13
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION
This Page Intentionally Left Blank
5.14
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.15
Owner Name and Address: _______________________________________________________________________________________
Change Order Number: __________________________________________________________________________________________
Date of Request: _______________________________________________________________________________________________
Name of Development: __________________________________________________________________________________________
PHFA Number: ________________________________________________________________________________________________
If executed by all signatories you are hereby authorized to make the changes described as follows: (Include description of work, quantities, unit prices,
labor, reason for change and scheduled time adjustments). Attach contractor’s quotes and additional justification as needed/ requested.
Description of Changes
CSI Division
#
Dollar Value of
Work
OH & P (2% Overhead
and 6% Profit)
Total Amount
Requested
PHFA Approved
Amount
Approval changes the Construction Contract by: ADDING $___________________ DEDUCTING ($__________________)
Check box if attaching additional owner funds (check, etc) in the amount of $_______________ payable to PHFA to fund change order.
Development Team Approval Signatures:
Design Professional Firm: ________________________________ By: ___________________________ Date: ___________________
Owner: _______________________________________________ By: ___________________________ Date ___________________
General Contractor: ____________________________________ By: ___________________________ Date: __________________
Bonding Company: _____________________________________ By: ___________________________ Date: __________________
Check box if Bonding Company intent letter is attached or is already on file with PHFA for this job
PHFA Approval Signatures: Technical Services Representative: _______________________________ Date: ___________________
Technical Services Division Director: ______________________________ Date: ___________________
Finance Division: ______________________________________________ Date: ___________________
APPENDIX 3, Form C5
Page 1 of 2
SECTION 5.04 Construction Contract Change Order Request Form C5
APPENDIX 3 Submission and Form Completion
(Rev 5/13) Instructions are printed on the back of this form
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.16
A. General Change Order Instructions
RETURN SIX ORIGINALLY SIGNED COPIES OF THIS CHANGE ORDER
TO THE PENNSYLVANIA HOUSING FINANCE AGENCY.
1. In order for this change order to be processed by PHFA, it must contain
all original signatures, with required support material attached. If any
required information is missing, the entire submission will be returned.
2. All work shall conform with applicable provisions of the Construction
Contract, Drawings, and Specifications unless otherwise specifically noted
herein.
3. This change order is not valid unless signed by Owner, Contractor,
Bonding Company (see note ‘E4’ hereon), Supervising Architect, PHFA
Technical Services Representative and Division Director as well as PHFA
Finance Personnel.
4. Either the Contractor or the Owner may initiate change orders. All
change orders must be approved by all parties and reviewed by the PHFA
Technical Services Representative prior to being sent to PHFA for its
approval.
5. Please submit change order increases and decreases as separate
change orders.
6. Change order increases must be paid to PHFA. The check must be
payable to the Pennsylvania Housing Finance Agency and attached to the
change order. If the Owner has paid more than the final net amount of all
“Add and Deduct” change orders, PHFA will return any overpayment when
the final closing takes place. In certain cases, change orders may be paid
from the construction contingency fund if included in the mortgage. If this is
the case, indicate the amount requested from the contingency account on
the line noted.
7. Change orders are cost certifiable. Savings (when all actual costs are
less than the mortgage amount) may be used to pay for change orders at
the sole discretion of PHFA.
8. PHFA will mail change orders it has signed to the Owner, General
Contractor and Supervising Architect.
9. The Owner, Architect or Contractor may request a change order to
cover additions, deletions or upgrades to the contract documents.
10. When it becomes necessary to make any of the above modifications to
the contract, a change order shall be prepared and submitted to PHFA for
approval within fifteen (15) business days after it has been determined that
the work is required. Changes not processed within this time frame may be
disapproved by PHFA, regardless of funding source.
11. Cost or credit for the work proposed by change orders will be
determined in accordance with the General Conditions AIA Document A201
and related PHFA SUPPLEMENTAL GENERAL CONDITIONS.
12. When the dollar value of the work has been determined by the
Contractor after compiling his/her own construction costs as well as the
construction cost of any and all related Subcontractors, the Contractor will
be allowed to add the following to that dollar value of the work: a)
Builders Overhead defined as expenses necessary to the operation of a
construction business and is limited to 2% of the dollar value of the work; b)
Builders Profit limited to 6% of the dollar value of the work; and c) any
additional bond premium that may be incurred as a result of the change
order work.
13. When work is deleted, the Contractor shall submit a change order for
the full value of the deletion. When an approved item of lesser quality is
installed, a change order shall be submitted for the difference between the
cost of the original item and the lesser substitution.
14. Except under emergency conditions, no changes in contract work shall
be made without a change order signed by the Owner and PHFA. Work
may be authorized on a time and material basis, but the procedure for
obtaining formal change orders remains the same. Owners will contact the
Technical Services Representative on emergency conditions and verify
emergency prior to the Contractor starting work on the change order.
15. Sufficient copies of letters, proposals and change orders must be
prepared so that each signatory has sufficient copies to process. Six
original PHFA Change Order Forms C5 are required for submission to
PHFA but only two complete copies of all change order substantiation
documentation need be submitted.
16. When a development is thirty (30) days behind the original
schedule, a change order must be submitted to the Architect by the
Contractor requesting a 30-day extension of time, with all necessary
documentation justifying the request. Subsequently additional no cost
time extension change orders may be submitted for review and approval
at any time during the course of the work.
B. Contractor Related Instructions
1. If a Contractor determines that items of work not covered in the
Contract Documents must be done, a request will be made by the
Contractor to the Architect within fifteen working days after discovery. If
a request for a Change Order is not submitted within this time, the
changes may be disapproved by PHFA.
2. Independent/unrelated credit change orders must be submitted on
separate forms. The exception being a credit given to accommodate
newly added change order work (i.e., a credit for vinyl tile and an add of
carpet at the same area may be on the same change order request; but
a credit for deleted landscaping and an add for window treatment must
be on separate change order forms).
3. Multiple independent credit change orders may be submitted on one
form.
4. Except for work of an emergency nature, all proposed changes in the
scope of contract work must be discussed during the job meetings prior
to that work commencing. All such changes in work scope must be
agreed to by the Owner, Architect, Contractor and PHFA. The
probability is high that any change order related to “design/build”
scenarios will be disapproved by PHFA.
5. The Contractor will submit the CHANGE ORDER FORM C5 to the
Architect with adequate substantiation as outlined below.
C. Owner Related Instructions
1. The Owner, with written approval of PHFA, may request extra work or
request changes by altering, adding or deducting from the contract work.
All such changes will be processed in accordance with PHFA’s change
order procedures. If the change order is an “add” and the contingency
has been expended, a check in the amount of the change order must be
attached to the change order request.
2. PHFA reserves the right to require the Owner to fund from sources
other than the contract contingency account, any/all change orders for
the provision of work which may have been previously removed from the
contract via Addendum, value engineering or similar agreements. This
stipulation is true regardless of the contingency account balance.
3. PHFA reserves the right to require the Owner to fund from sources
other than the contract contingency account any/all change orders for
provision of work, for fees, for permits, for design costs or similar
required to satisfy utility providers and/or Governing Municipalities.
Design and/or review fees associated with additional utility work, hook-
up fees, service extensions, etc., also fall under this stipulation. This
stipulation is true regardless of the contingency account balance.
4. These change orders must be submitted within fifteen working days
after it has been determined that the work is required. Any change
orders submitted after this time frame may not be approved by PHFA.
D. Architect Related Instructions
1. Upon receipt of a request for a change order and after review as
indicated in the change order procedures, the Architect will forward
his/her recommendations to the Owner, together with all proper
substantiation. The recommendations shall be in written form and refer
to the Contract Documents defining where and why the change is
warranted.
APPENDIX 3
Page 2 of 2
2. The Architect will forward this information to the Owner after it is
received from the Contractor. Any change orders not processed and in
the possession of PHFA within the fifteen day limit may be disapproved
by PHFA.
E. Change Order Submission Procedures for All Parties
1. Following the request for a change in the work, the Architect shall
address a letter to the Contractor (with copies to the Owner and PHFA)
including the following information and requesting a change order from
the Contractor: Nature and extent of work added, deleted or changed,
supplementary drawings as required, reason for change. Should the
Contractor discover a necessity for a change or substitution, he shall
first call the Architect and obtain approval to proceed with the request.
2. The Contractor shall prepare and submit the final PHFA Change
Order Form C5 to the Architect indicating the following: Nature and
extent of work added, deleted or changed, supplementary drawings,
specifications and other pertinent documentation, reason for change,
detailed cost breakdown (labor and materials, supporting invoices) or
lump sum as required by Contract Documents), the effect the change
order will have on the construction schedule indicated as the number of
additional or fewer days required to complete the contract work.
3. The Architect, upon receipt of the Contractor’s change order, and
after review as indicated below, shall forward his recommendations to
the Owner, together with all proper documentation. The observing
Architect, when applicable, shall: Review the change for technical
correctness and comment, review the change for reasonable cost,
include a statement explaining why the modification to Contract
Documents was required, and recommend acceptance, rejection, cost
revisions or alternate solutions. Sign the change order and forward it to
the Owner.
4. The Owner will review the change order and suggestions received
from the Architect and accept or reject it. If accepted, the change order
shall be signed by the Owner, Contractor, Bonding Company,
PHFA Technical Services Representative and other required governing
agencies. In order to expedite processing of change orders, the
Contractor may secure documentations from their bonding company at
the start of the contract work indicating the bonding company’s intent
and dollar value limit to which they will provide coverage. Such
documentation must be on official bonding company letterhead and
must bear the seal of that bonding company along with appropriate
signature(s). A copy of such document may be affixed to each change
order request in lieu of the bonding company’s individual
approvals/signatures. If the contingency fund is exhausted or if PHFA
requests owner funding, the Owner shall attach a check to the change
order in a sufficient amount to cover the cost.
5. Upon receipt of the data in “E4” (immediately above) and the check
from the Owner, PHFA shall: Review the entire package, accept, reject
or suggest modifications, authorize payment when included in the
Contractor’s regular requisition, execute and return three copies of the
change order to the Owner.
6. Change Order Log - At the first inference that a change is eminent,
it shall be numbered and recorded on the Change Order Log with an
estimated cost. When changes are approved, they shall be renumbered
and entered on the approved side of the log. This log is the responsibility
of the Architect and shall be updated and submitted to the Technical
Services Representative at each payout meeting.
ALL INSTRUCTIONS AND PROCEDURES ARE SUBJECT TO
CHANGE BY PHFA AT ANY TIME. SHOULD CHANGES OCCUR
DURING THE WORK THE PHFA TECHNICAL SERVICES
REPRESENTATIVE WILL ALERT AND INSTRUCT ALL PARTIES AS
TO WHAT THE CHANGES ARE AND HOW THEY MAY AFFECT THE
CONSTRUCTION CONTRACT OR THE WORK.
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.17
SECTION 5.05
PROCEDURES OCCUPANCY
These procedures are to clarify the policies of the Pennsylvania Housing Finance Agency with
respect to the issuance of Certificate(s) of Occupancy by PHFA and the sanctions to be imposed
by PHFA in the event of violation of these policies.
1. Certificates of Occupancy shall be issued only for completed sections. A completed section is
defined as follows:
A. Garden Apartment Completed buildings.
B. Townhouses Completed buildings.
C. Multi-level (high-rise, mid-rise, etc.) Completed building(s) including all floors and
commercial areas.
Each development will be designated as one of the above definitions at the preconstruction
meeting, and Certificate(s) of Occupancy will be issued based on those designations.
2. Sections as indicated above which are prepared for occupancy during the construction of a
development shall be completed and ready for punch listing by the Technical Services
Representative, Contractor, Architect and Owner not less than twenty (20) working days prior to
the anticipated date of occupancy. The punch list items and necessary corrective work must be
completed not more than fifteen (15) days from the date the list is prepared. The anticipated date
of occupancy shall be defined as the date the unit is made available for marketing.
3. All punch list procedures and documentation to be executed as outlined in this Guide.
4. The one-year guarantee period for dwelling units and related support facilities will commence as
of the date of substantial completion. Guarantees for all other areas will start at the construction
completion date.
APPENDIX 4
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.18
SECTION 5.06
PUNCH LIST FORM
Development: ________________________________ Bldg. No.: _________________________
Inspection Date(S): ___________________________
PHFA No.: ___________________ Apt. No.: _______ Architect: ________________________
_________________________________________________________________________________________________________
CODE:
1. Chipped/scratched 5. Missing 9. Repair 13. Sand
2. Faulty 6. Adjust 10. Leak 14. Paint touch-up
3. Broken/damaged 7. Touch-up 11. Caulk 15. Torn
4. Dented/nicked 8. Replace 12. Clean 16. Other ___
NO.
OK
ENTRANCE
NO.
OK
DINING ROOM (cont.)
NO.
OK
BATHROOM
Door
Windows & screens
Tub/showers
Lock/deadbolt
Sliding door screen & lock
Shower heads
Weather stripping
S/W plates/receptacles
Shower rods
Door sills
Towel bars
Chain lock
NO.
OK
STORAGE/HEATER
Viewer/knocker
Ceiling
NO.
OK
1
ST
BEDROOM
Walls & base
Door
NO.
OK
STAIRWAY
Heater & AC
Ceiling
Stringer
Hot water heater
Walls & base
Trim
Floor
Carpeting
Carpeting
Closet door
NO.
OK
CRAWL SPACE
Closet/shelves
NO.
OK
KITCHEN
Clean
HVAC-grilles/
Ceiling
Vapor barrier
reg. baseboard heat
Walls & base
Heat tapes
Window & screen
Floor
Light fixtures
NO.
OK
BATHROOM 1
NO.
OK
2
ND
BEDROOM
Closet doors
Ceilings
Door
Windows & screens
Walls & base
Ceiling
Closet/shelves
Floors
Walls & base
Refrigerator
Doors
Carpeting
Stove
Light fixtures
Closet door
Exhaust Hood &/or fan
Exhaust fans
Closet/shelves
Counter top
GFI receptacles
HVAC-grilles/
Sink
Medicine cabinets
reg. baseboard heat
Waste disposal
Mirrors
Window & screen
Dishwasher
Sinks
Cabinets
Vanities
NO.
OK
3
RD
BEDROOM
Toilets
Door
NO.
OK
LIVING ROOM
Tub/showers
Ceiling
Ceiling
Shower heads
Walls & base
Walls & base
Shower rods
Carpeting
Carpeting
Towel bars
Closet door
HVAC-grilles/
Closet/shelves
reg. baseboard heat
NO.
OK
BATHROOM 2
HVAC-grilles/
S/W
Ceilings
reg. baseboard heat
TV outlet
Walls & base
Window & screen
Thermostat
Floors
Window & screens
Doors
NO.
OK
4
TH
BEDROOM
Light fixtures
Door
NO.
OK
DINING ROOM
Exhaust fans
Ceiling
Ceiling
GFI receptacles
Walls & base
Walls & base
Medicine cabinets
Carpeting
Light fixture
Mirrors
Closet door
HVAC-grilles/
Sinks
Closet/shelves
reg. baseboard heat
Vanities
HVAC-grilles/
Carpeting
Toilets
reg. baseboard heat
Window & screen
APPENDIX 5
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.19
SECTION 5.07
PENNSYLVANIA HOUSING FINANCE AGENCY
CERTIFICATE OF SUBSTANTIAL COMPLETION
DEFINITION OF DATE OF SUBSTANTIAL COMPLETION
The date of Substantial Completion of the work or designated portion thereof is the date certified by
the Architect when construction is sufficiently complete in accordance with the Contract Documents
and is in a market ready condition. After such date, the Owner may occupy the designated portion
thereof for the use of which it is intended. This begins the one year guarantee period for these units
and their support facilities.
______________________________________________________________________
Development:__________________________ PHFA No.: __________ Date: ________
Architect: _________________________Contractor:____________________________
Owner/Developer: ________________________________________________________
______________________________________________________________________
DESIGNATED AREA DEEMED SUBSTANTIALLY COMPLETED
BUILDING ADDRESS
NO. OF
UNITS
APARTMENT
IDENTIFICATION
TYPE OF UNITS
(1, 2, 3 BEDROOMS)
ITEMS TO BE CORRECTED OR COMPLETED
(Attach list to this form)
The work performed and described under this Certificate has been reviewed and found to be
substantially complete. Substantial Completion Date is hereby established as
__________________.
A list of items to be completed or corrected, as prepared by the Architect, is attached. The failure to
include any items does not alter the responsibility of the Contractor to complete all work in
accordance with the Contract Documents.
APPENDIX 6, Page 1 of 2
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.20
________________________ ______________________ ________________
Architect Firm Date
The Contractor must complete or correct the work on the items listed above within fifteen (15)
working days, except those noted as seasonal in nature. Completion of such seasonal items must
be accompanied as soon as possible.
________________________ ______________________ ________________
Contractor Firm Date
The Owner accepts the work as substantially complete and will assume full possession thereof on
the date of completion of the items listed above.
________________________ ______________________ ________________
Owner Firm Date
The Pennsylvania Housing Finance Agency has reviewed the work and accepts it as being
substantially complete as defined herein. Failure to complete or correct the items listed above within
the specified dates will result in the delay of issuance of the Certificate of Occupancy.
________________________ ______________________ ________________
Technical Services Rep PHFA Date
________________________ ______________________ ________________
Firm Date
________________________ ______________________ ________________
Firm Date
APPENDIX 6, Page 2 of 2
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.21
SECTION 5.08
PENNSYLVANIA HOUSING FINANCE AGENCY
CERTIFICATE OF OCCUPANCY
Development:_______________________________ Date: ______________________
PHFA No.:__________________________________ Occupancy No.: ______________
Owner:____________________________________ Stage No.:___________________
Number of Units:____________________________ Building:____________________
Of the residential units for the above referenced project, the below listed apartments are deemed
ready for occupancy and constitute ______% of the total occupancy of this project.
Occupancy date is hereby established as _________________, 20__.
This certificate does not constitute a waiver or release of the General Contractor from all obligations
under the Contract Documents, generally, and in specific, shall not operate to release the General
Contractor from his continuing obligation, among other things, to correct all latent defects during the
One-year Guarantee Period.
PENNSYLVANIA HOUSING FINANCE AGENCY
APPROVED:
________________________________
Director of Technical Services
cc: Technical Services Rep. Architect Legal
Lisa Case Contractor Kyle Matter
Shana Erdley PHFA Dev. Officer
APPENDIX 7
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.22
SECTION 5.09
PROCEDURES FINAL INSPECTION/CONSTRUCTION COMPLETION
After execution and acceptance of the Certificate(s) of Substantial Completion, a Final Inspection will be
held to determine the acceptability of the development as a whole and to determine the “Date of Actual
Construction Completion” as required in the Contract Documents. The procedures for this Final
Inspection shall be as follows:
1. The final inspection shall be conducted by the Architect and shall include all the interior and
exterior systems.
2. The final inspection shall be attended by the Architect and Representatives of PHFA, Owner and
Contractor. The Owner, at his discretion, may authorize the Architect to represent him at the final
inspection.
3. Prior to the execution of the final inspection form, all outstanding punch list items must be
complete, with the exception of seasonal and miscellaneous items approved by the Architect and
PHFA. These incomplete items will be listed on the final inspection form with a corresponding
estimated value required to complete them. A sum equal to 200% of these amounts will be
withheld from the final construction draw and will be released when the items are complete.
4. The final inspection form and punch list shall be signed by the Owner, Supervising Architect,
Contractor and PHFA Technical Services Representative and forwarded to PHFA for review and
establishment of the “Date of Actual Construction Completion.”
5. If the above referenced form is in compliance with the procedures as stated, PHFA will issue a
“Certificate of Construction Completion” specifying the “Date of Actual Construction Completion”.
6. The One-year Guarantee Period for dwelling units and related support facilities will commence as
of the date of substantial completion. Guarantee for all other areas will start at the construction
completion date.
APPENDIX 8
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.23
SECTION 5.10
PENNSYLVANIA HOUSING FINANCE AGENCY
FINAL INSPECTION
Date of Final Inspection: _______________________________________
Development Name:___________________________________________
PHFA No.: ____________________
This document hereby certifies that those persons who have executed this document have attended the
Final Inspection of the above referenced development in order to determine the Date of Actual
Construction Completion and have found the following punch list items which need to be completed or
corrected:
(A) FINAL INSPECTION PUNCH LIST ITEMS: (include attachment if necessary)
ITEM VALUE
1. ________________________________________________________________
2. ________________________________________________________________
3. ________________________________________________________________
4. ________________________________________________________________
5. ________________________________________________________________
6. ________________________________________________________________
Amount withheld shall be 200% of the value.
The Architect for the above referenced development, in accordance with the Owner/Architect Agreement
for construction observation, hereby certifies that based on his/her professional observations and
inspections in accordance with his/her contract, the above referenced development has been completed
in compliance with the Contract Documents and that, in his/her professional opinion, the development is
in good and tenantable condition. The Architect also requests that the date of the Final Inspection be
considered as the “Date of Actual Construction Completion”. This will start the One-year Guarantee
Period for all areas not previously covered in the Substantial Completion Certificate(s).
____________________________________ _____________________________________
Observing Architect/Date Owner/Date
____________________________________ _____________________________________
Contractor/Date PHFA Technical Services Rep/Date
APPENDIX 9
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.24
SECTION 5.11
PENNSYLVANIA HOUSING FINANCE AGENCY
CERTIFICATE OF CONSTRUCTION COMPLETION
Owner:__________________________________________ Date: _______________
Development Name:________________________________ PHFA No: ____________
DATE OF ACTUAL CONSTRUCTION COMPLETION
(DATE)
The Pennsylvania Housing Finance Agency, being in receipt of a document known as the “Final
Inspection” form, and that document having been executed by the Supervising Architect and
Representatives of the Agency, Owner and Contractor, hereby issues this Certificate of
Construction Completion based on the below referenced stipulations.
The punch list items have been completed and corrected except those items awaiting seasonal
opportunity, which items have been specified on the “A” portion of the “Final Inspection” form.
It is understood by all parties concerned that the above referenced “Date of Actual Construction
Completion,” (DATE), is that date on which the Agency deems the project to have completed the
construction phase as required under the terms and conditions of the Contract Documents.
The Supervising Architect has certified that the project is complete as a whole to the best of
his/her knowledge, information and belief and is in compliance with the terms and conditions of
the Contract Documents and that the project is, in his/her professional opinion, in good and
tenantable condition.
That it is understood that this Certificate does not in any way imply that the project has completed
Cost Certification or any other requirements of any other Division of the Pennsylvania Housing
Finance Agency.
PENNSYLVANIA HOUSING FINANCE AGENCY
APPROVED:
________________________________
Director of Technical Services
cc: Technical Services Rep. Architect Legal
Lisa Case General Contractor Lisa Lutz
Shana Erdley PHFA Dev. Officer Kyle Matter
APPENDIX 10
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.25
SECTION 5.12
PROCEDURES CONSTRUCTION PAYOUTS
Construction Payouts will be made monthly and derived from the construction cost breakdown
established in the field at the first Payout Meeting. The revised breakdown will be reviewed and approved
by the Contractor, Architect, PHFA Technical Services Representative and other Local Governing
Authorities.
The second and all subsequent payouts shall be established using PHFA’s computerized work sheet.
One week prior to the cut-off date, the Technical Services Representative will forward a work sheet to the
General Contractor to establish his payout and return a completed copy to the Technical Services
Representative shortly prior to the cut-off date.
At the payout meeting, the Contractor, Architect and Technical Services Representative will do a walk-
through to verify the numbers, after which four copies of the approved work sheet shall be signed by all
parties. Two copies shall be given to the Technical Services Representative, one copy to the Architect
and the other retained by the General Contractor.
The General Contractor will then prepare the AIA DOCUMENT G702 APPLICATION AND CERTIFICATE
FOR PAYMENT based on the approved work sheet figures and submit it to the Architect.
Ten percent (10%) of each payment request for a construction item made by the contractor will be retained
by either the Agency or other related lenders. The percentage retained may be reduced to five percent (5%)
after construction has been fifty percent (50%) completed. Upon issuance of the Agency’s Certificate of
Substantial Completion, this amount may be reduced to two and one-half percent (2 ½ %). In the event of
multiple Certificates of Substantial Completion being issued for phased projects, reduction to two and one-
half percent (2 ½ %) will be considered only after the final phase of the whole is accepted. The balance due
to the contractor shall be payable at final loan closing provided the work is fully completed and contractor has
complied with all provisions of the Construction Contract to Owner's and Agency’s satisfaction, including, but
not limited to, submission and approval of Contractor's Certificate of Actual Cost to the Agency and receipt of
all Certificates of Occupancy for all units.
APPENDIX 11
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.26
SECTION 5.13
CONTRACTOR PAYMENT FORMS
APPENDIX 12 APPLICATION AND CERTIFICATE FOR PAYMENT,
AIA DOCUMENT G702
APPENDIX 13 CONTINUATION SHEET, AIA DOCUMENT G703
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.27
SECTION 5.14
PENNSYLVANIA HOUSING FINANCE AGENCY
RENTAL HOUSING PROGRAM
GENERAL CONTRACTOR’S ACTUAL CONSTRUCTION COST CERTIFICATION
Development Name: _______________________________________________
PHFA No.:________________________________________________________
Contractor Name: _________________________________________________
We herein certify to PHFA the following:
1. The total construction cost of the development is $___________________as detailed below.
A. Original Contract $______________________
B. Approved Change Orders $______________________
C. Total $______________________
2. All construction work in connection with the development has been completed.
3. That all construction cost that has been incurred by the Contractor under the Construction
Contract” has been fully paid, including payment to all Subcontractors, except as follows:
A. Retention $__________________
B. $__________________
C. $__________________
_______________________________________________ ___________________
Signed Date
_______________________________________________
Typed or Printed Name and Title
APPENDIX 14
SUBMISSION GUIDE FOR ARCHITECTS, 2016 EDITION 5.28
SECTION 5.15
CONTRACTORS CERTIFICATION OF COMPLIANCE
WITH DESIGN REQUIREMENTS FOR ACCESSIBLE HOUSING
Development: _________________________________________ PHFA No.: __________
Check Appropriate: _____ New Construction
_____ Substantial Rehabilitation
_____ Moderate Rehabilitation
_____ Townhouse _____ Elevator
_____ Walkup Apartments _____ Non-elevator
To the best of my knowledge and belief, I certify that I have constructed the referenced facility in
conformance with the Contract Documents prepared by ______________________, the
Architect.
In reference to the above, I hereby further certify as follows:
*The development contains a total of ________ rental dwelling units.
*Of this total, ________ units are accessible.
*Of this total, ________ units have been constructed to be adaptable.
**OF THIS TOTAL, ________ UNITS HAVE BEEN CONSTRUCTED TO INCLUDE FEATURES
FOR INDIVIDUALS WITH HEARING OR VISION IMPAIRMENT.
Contractor:
Signed: ________________________________________________ Date: ______________
(To Be Signed by Authorized Officer of Construction Firm)
Acknowledged and Accepted by Owner:
Signed: _______________________________________________ Date: ______________
NOTES:
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
This document must be completed, signed and acknowledged by all pertinent parties prior to PHFA
issuing a Certificate of Occupancy. One such form must be completed for each stage of phased
occupancy. Multiple buildings may be incorporated onto one form but must be noted as such. Attach this
form to the executed Certificate of Substantial Completion documentation.
APPENDIX 15