Crane, Hoist and Sling Safety Program
Overview:
Cranes, hoists and slings pose a serious safety hazard if not used properly. It is the
intent of Yale University to ensure all users and owners are trained in the safe operation
and the hazards of using cranes, hoists and slings. All equipment, as such, must be
safely maintained.
Scope & Applicability:
This program applies to all faculty, staff and students at all Yale University locations.
This program covers the following cranes and hoists: overhead and gantry cranes,
semi-gantry cranes, cantilever gantry cranes, wall cranes, monorail cranes, bridge
cranes, single girder cranes, overhead hoists, engine hoists or winches, and other
hoists and cranes having the same fundamental characteristics.
This program does not cover cab operated cranes and mobile cranes (wheel-mounted,
rough-terrain, all-terrain, commercial truck-mounted, and boom truck cranes).
The program covers the following types of slings used at Yale University: alloy steel
chain, wire rope, metal mesh, natural and synthetic fiber rope, and synthetic webbing.
Page 2 of 24
New Haven, Connecticut
Table of Contents:
1.0 References
2.0 Responsibilities
3.0 Definitions
4.0 General Requirements
5.0 Training
6.0 Inspections
7.0 Maintenance
8.0 Recordkeeping
9.0 Contractors
Appendix A: Monthly Crane/Hoist Frequent Inspection Checklist
Appendix B: Annual Crane/Hoist Periodic Inspection Checklist
Appendix C: Annual Sling Periodic Inspection Checklist
Appendix D: Examples of Cranes and Hoists
Appendix E: Examples of Slings
Appendix F: Crane and Hoist Training Certification Form
Appendix G: Safe Work Practices for Cranes, Hoists and Slings
Appendix H: Bridge Crane Operator Evaluation Form
Appendix I: Instructions for Conducting Bridge Crane Operator Evaluations
Page 3 of 24
New Haven, Connecticut
1.0 References:
(The following have been used as references in the development of this program)
Personal Protective Equipment Program
Lockout Tagout Program
OSHA Publication Sling Safety - #3072
OSHA Standard Overhead and Gantry Cranes 29 CFR 1910.179
OSHA Standard Slings 29 CFR 1910.184
ANSI/ASME B30.2 Overhead and Gantry Cranes
ANSI/ASME B30.9 Slings
ANSI/ASME B30.10 Hooks
ANSI/ASME B30.11 Monorails and Underhung Cranes
ANSI/ASME B30.16 Overhead Hoists (Underhung)
ANSI/ASME B30.17 Overhead and Gantry Cranes (Top Running Bridge,
Single Girder, Underhung Hoist)
HMI (Hoist Manufacturers Institute) Manually Lever Operated Hoist Inspection
and Hoist Maintenance Personnel Manual
2.0 Responsibilities:
2.1 Department/School
Designate individuals as the Responsible Person for the implementation of
this program within their work area.
Ensure adequate funding is available to support this program.
2.2 Responsible Person
Ensure that responsibilities assigned within this program are carried out
within their administrative work area.
Actively support this program as part of the work area’s overall safety effort.
Be thoroughly informed of the contents of this program and its application to
their areas of responsibility and authority.
Ensure equipment users comply with all provisions of this program.
Ensure equipment users receive training appropriate to their assigned tasks
and maintain documentation of such training.
Ensure equipment users are provided with and use appropriate protective
equipment.
Take prompt corrective action when unsafe conditions or practices are
observed.
Investigate injuries and incidents within their work unit related to crane, hoist
and sling usage.
2.3 Department of Environmental Health and Safety (EHS)
Assist work units in implementing the provisions of this program.
Periodically review and update this written program.
Page 4 of 24
New Haven, Connecticut
Periodically evaluate the overall effectiveness of this program.
Review and approve competent trainers and evaluators.
Maintain an inventory of equipment covered by this program.
Determine intervals for frequent and periodic inspections.
Investigate accidents, incidents, and near misses related to cranes on
campus.
2.4 Equipment Users
Follow the work practices described in this program, including the use of
appropriate protective equipment.
Attend all training required by this program.
Immediately report any unsafe conditions or concerns related to cranes,
hoists or slings to their Responsible Person.
3.0 Definitions:
Authorized Person (Repair): Someone with training and experience pertaining to crane
and hoist repair, with the expertise to address the specific safety considerations that are
unique to cranes and hoists.
Bridge: That part of a crane consisting of girders, trucks, end ties, foot walks, and drive
mechanism which carries the trolley(s).
Bridge Crane: A load lifting system consisting of a hoist which moves laterally on a
beam, girder, or bridge which in turn moves longitudinally on a runway made of beams
and rails. Loads can be moved to any point within a rectangle formed by the bridge
span and runway length.
Bumper: A device for reducing impact when a moving crane or trolley reaches the end
of its permitted travel, or when two moving cranes or trolleys come into contact. This
device may be attached to the bridge, trolley or runway stop.
Competent Trainer: A person who has demonstrated familiarity with the type of
crane/hoist in their work area. A contractor or equipment vendor who has experience
training, crane/hoist operation and is familiar with the equipment is also permitted to be
a Competent Trainer.
Competent Evaluator: A person in the department/work area who is experienced and
competent with the crane, and is familiar with the equipment and its safe operation. The
classroom portion of the crane/hoist training must have been successfully completed to
be considered competent in regard to conducting the evaluation portion of the crane
training. The competent evaluator could be, but is not limited to, a certified operator,
supervisor/manager or safety officer.
Page 5 of 24
New Haven, Connecticut
Crane: A machine for lifting and lowering a load and moving it horizontally, with the
hoisting mechanism an integral part of the machine. Cranes can be driven manually or
by power.
Department/School: Unit designated for providing necessary funding to meet the
requirements of this program to include inspections and repairs.
Designated Person: Person selected or assigned by Yale University or Yale
University’s representative as being qualified to perform specific duties, including
periodic inspections.
Drum: The cylindrical member around which rope is wound for lifting or lowering the
load.
End Truck: An assembly consisting of the frame and wheels which support the crane
girder(s) and allow movement along the runway.
Floor operated crane: Crane controlled by an operator on the floor or an independent
platform using a pendant or non-conductive rope.
Gantry crane: A crane that has a hoist in a trolley which runs horizontally along gantry
rails, usually fitted underneath a beam spanning between uprights which themselves
have wheels so that the whole crane can move at right angles to the direction of the
gantry rails.
Hoist: A suspended machinery unit that is used for lifting or lowering a freely
suspended (unguided) load.
Latch Hook: A type of hook with a mechanical device to close the throat opening of the
hook.
Limit Device: A device that is operated by some part or motion of a power-driven hoist
to limit motion.
Load: The total superimposed weight of the load block and hook.
Monorail: A trolley suspension crane hoist, whose trolley is suspended from a single
rail. This type of crane hoist is used to move a load horizontally.
Overhead crane: A crane with a movable bridge carrying a movable or fixed hoisting
mechanism and traveling on an overhead fixed runway structure.
Rated Load (Capacity): The maximum load designated by the manufacturer for which
a crane or individual hoist is designed and built.
Page 6 of 24
New Haven, Connecticut
Reeving: A system in which a rope or chain travels around drums, sheaves or
sprockets.
Responsible Person: A person that is accountable for the duties as assigned above.
This person could be a Principal Investigator (PI) or manager of the area.
Rope: Refers to wire rope unless otherwise specified.
Sheave: A grooved wheel or pulley used with a rope or chain to change direction and
point of application of a pulling force.
Trolley: The unit which travels on the bridge rails and carries the hoisting mechanism.
Wall mounted jib crane: A crane with a jib and with or without a trolley. The wall crane
is supported from a side wall or columns of a building.
4.0 General Requirements for Cranes, Hoists and Slings:
4.1 The Department/School must notify Environmental Health and Safety (EHS)
when a crane or hoist is installed to maintain an inventory.
4.2 If the need arises to operate crane or hoists not owned by Yale University,
contact EHS for further guidance.
4.3 Only trained users shall operate a crane or hoist.
4.4 Cranes, hoists and slings shall go through frequent and periodic inspections.
Intervals for frequent and periodic inspections depends upon the nature of the
critical components of the crane and the degree of their exposure to wear,
deterioration or malfunction. Inspection intervals for cranes and hoists used
infrequently will be determined in agreement with EHS (See 6.6).
4.5 Operators must perform a pre-use inspection of cranes, hoists and
chains/slings.
4.6 Any unsafe condition noted during an inspection shall be corrected before the
equipment is used. Unsafe equipment must be tagged “Out of Service, Do
Not Use.”
4.7 Operators shall comply with the manufacturer's specifications and limitations
applicable to the operation of the equipment.
4.8 Where manufacturer's specifications are not available, the limitations
assigned to the equipment shall be based on the determinations of a qualified
engineer competent in this field and such determinations will be appropriately
documented and recorded.
4.9 Operators shall follow safe work practices when operating cranes, hoists and
slings. (See Appendix G).
4.10 Purchase and operation of all equipment covered by this program requires
approval by EHS.
4.11 Assignment of a designated Department/School and Responsible Person is
required.
4.12 All equipment must include a capacity label.
Page 7 of 24
New Haven, Connecticut
4.13 All equipment must be installed and maintained to meet applicable OSHA and
ANSI standards. Only authorized personnel shall perform repairs and
adjustments.
4.14 All replacement parts shall be the same design as the original or an
equivalent design as designated by the manufacturer.
5.0 Training:
5.1 Training must be completed prior to any use of a crane or hoist. Training of
crane and hoist operators at Yale University is a two-step process for most
cranes/hoists which consists of classroom instruction & hands-on training.
5.2 Classroom instruction, hands-on training and operator evaluations can be
conducted by either a competent trainer in the work unit, the equipment
manufacturer, a safety consultant and/or a vendor who specializes in
crane/hoist training. Documentation of these trainings will be input into the
Yale Training Management System.
5.3 In addition to the above requirements, a documented operator evaluation is
required for operators of Bridge Cranes. (Appendix H)
5.4 Hands-on training and hands-on evaluation portions of the training can also
be conducted by a competent user in the department/work unit who is
experienced and competent with the equipment. This person could be a
trained operator, supervisor/manager or safety officer.
5.5 Training must be specific to the type of equipment being used.
5.6 Training shall include the following:
5.6.1 Characteristics of safe crane and hoist operation;
5.6.2 Inspection procedures;
5.6.3 Basic load handling considerations;
5.6.4 Operator responsibilities;
5.6.5 Communication used during crane and hoist operation; and
5.6.6 Hands-on equipment training.
5.7 Trainees must successfully complete hands-on training before being allowed
to operate the equipment independently. Trainees will be given adequate
supervision and time to learn basic operating skills.
5.8 Refresher training in relevant topics will be provided to a crane or hoist
operator when any of the following occur:
5.8.1 The operator has been observed using the equipment in an unsafe
manner.
5.8.2 The operator has been involved in an accident or a near-miss incident.
5.8.3 The operator is assigned to operate a different type of equipment.
5.8.4 A condition in the workplace changes in a manner that could affect
safe operation of the equipment.
5.8.5 The crane, hoists and slings standards are updated and conflict with
this program.
6.0 Inspections for Cranes, Hoists and Slings:
The Responsible Person shall ensure the following inspections are completed:
Page 8 of 24
New Haven, Connecticut
6.1 Pre-Use Inspection
6.1.1 Prior to use the operator shall visually inspect the crane, hoist and/or
slings for defects.
6.1.2 The pre-use inspection will identify conditions that could affect the safe
use of the equipment.
6.1.3 Operators must immediately report any unsafe crane conditions to the
Responsible Person who must ensure the necessary arrangements
are made for repair.
6.2 Frequent Inspection (Crane and Hoists) (See Appendix A)
6.2.1 A documented frequent inspection of all cranes and hoists shall be
performed. These inspections must be performed by a designated
person.
6.2.2 Monthly inspections are to be performed. If a crane is rarely used, that
interval will be determined in agreement with EHS.
6.3 Periodic Inspection (Cranes and Hoists) (See Appendix B)
6.3.1 A documented periodic inspection of all cranes and hoists shall be
performed by a designated person.
6.3.2 All cranes and hoists shall be labeled or marked to show date of last
annual inspection.
6.3.3 Intervals for periodic inspections will be determined in agreement with
EHS, but must be performed at least annually.
6.4 Periodic Inspection (Chains and Slings) (See Appendix C)
6.4.1 A documented periodic inspection of all chains and slings shall be
performed by a designated person.
6.4.2 Each chain and sling will have a permanent tag physically attached.
6.4.3 Each chain and sling will be traceable to an NIST standard.
6.4.4 Intervals for periodic inspections will be determined in agreement with
EHS, but must be performed at least annually.
6.5 If any unsafe conditions exist, the equipment shall be removed from service
and tagged “Out of Service, Do Not Use.”
6.6 Cranes and Hoists Not in Regular Use
6.6.1 A unit which has been idle for a period of one month or more shall be
given a frequent inspection before placing in service. When applicable,
a thorough inspection of wire ropes must be completed.
6.6.2 A unit which has been idle for a period of six months or more shall be
given a frequent and periodic inspection before placing in service.
6.7 Prior to initial use, all new, altered, modified or repaired cranes and hoists
shall have the following testing performed by the installation company or third
party:
6.7.1 Hoisting and lowering
6.7.2 Trolley travel
6.7.3 Bridge travel
6.7.4 Limit switches, locking and safety devices
6.7.5 Load Tests
6.7.5.1 Shall not be more than 125% of the rated load unless
Page 9 of 24
New Haven, Connecticut
otherwise recommended by the manufacturer.
7. Maintenance:
Preventive maintenance shall be performed as prescribed by the
manufacturer as detailed in the owner's manual.
8. Recordkeeping:
The Responsible Person shall maintain the following records to meet the
requirements of this program:
8.1 A listing of all applicable cranes, hoists and slings.
8.2 A record of training which includes: (Use Appendix F or equivalent)
8.2.1 Name of trainer.
8.2.2 Name of operator.
8.2.3 Date of training (classroom, hands-on training, hands-on evaluation).
8.3 The responsible party will maintain the following records to meet the
requirements of this program:
8.3.1 Copies of all frequent inspection records for one year after completion.
8.3.2 Copies of periodic and annual inspection records for at least four
years.
8.3.3 Copies of repair records for the life of the equipment.
8.3.4 Copies of load test results for the life of the equipment.
8.4 EHS is responsible for auditing the required records to ensure that the
requirements of this program are met.
8.5 EHS will receive and retain training records for training they have provided.
9.0 Contractors:
Contractors are required to follow all applicable OSHA regulations and
manufacturer’s instructions. Contractors are not permitted to use any crane, hoist or
sling owned by Yale University unless given documented authorization by the
responsible owner and Environmental Health and Safety.
Page 10 of 24
New Haven, Connecticut
Appendix A
Crane/Hoist Frequent Inspection Checklist
Location:
ID number or identifier:
Inspector Name (print):
Date:
Inspection Item
Yes
N/A
Load rating marked on each side of the crane.
Load rating of the hoist marked on the hoist or its load block
and legible from the ground? (If the crane has more than one
hoisting unit, each hoist shall have its rated load marked on it
or its loading block and this marking shall be clearly legible
from the ground.)
At least 3 inches of overhead clearance and 2 inches laterally
between crane and obstructions.
All controller functions labeled and legible.
All operational controls and functional operating mechanisms
working properly, properly adjusted and no unusual sounds.
Upper limit switch operating properly. It shall be tested with no
load on the hook. Extreme care shall be exercised; the block
shall be "inched" into the limit device or run in at slow speed.
Excessive wear of components on any functional operating
mechanisms.
Deterioration or leakage in lines, tanks, valves, drain pumps,
and other parts of the air or hydraulic system.
Excessive dirt, grease, or foreign matter.
Deformation and/or cracking of the hook, load block, drums
and/or sheaves.
Safety latch on crane/hoist load block that automatically
closes.
Comments:
Page 11 of 24
New Haven, Connecticut
Appendix B
Crane/Hoist Periodic Inspection Checklist
Location:
ID number or identifier:
Inspector Name (print):
Date:
#
Inspection Item
Yes
No
N/A
1
Conduct frequent inspection of equipment. Does it pass the
frequent inspection? (See Appendix A)
2
Any deformed, cracked, or corroded members?
3
Are there worn, cracked, or distorted parts such as pins,
bearings, wheels, shafts, gears, rollers, locking and clamping
devices, bumpers, and stops?
4
Is there excessive wear or improper operation of the brake
system parts, linings, pawls, chain sprockets or ratchets?
5
Any cracked or worn sheaves and drums?
6
Are there loose or missing bolts, nuts, pins or rivets?
7
Is there any signs of pitting or deterioration of controllers, master
switches, contacts, limit switches, and push button stations?
8
Are load, wind, and other indicators properly operating?
9
Are the gasoline, diesel, electric, or other power units performing
properly?
10
Are stops provided at the limit of travel of the trolley?
11
Corroded, cracked, bent, worn, or improperly applied end
connections?
12
Load chain reeving for compliance with hoist manufacturer’s
recommendation?
Hook:
Page 12 of 24
New Haven, Connecticut
13
Are there any gouges, nicks, weld spatter, corrosion,
deformation, cracks?
14
Has the hook throat opening increased 5%, not to exceed ¼ inch
(6 mm), more than the normal throat opening measured at the
narrowest point?
15
Is there any bend or twist from the plane of the unbent hook?
Wire Rope/Chain:
16
Is there excessive drive chain stretch?
17
Test the hoist under load in lifting and lowering directions and
observe the operation of the chain and sprockets. Does the
chain feed smoothly into and away from the sprockets?
18
Does the chain bind, jump, or is noisy? If so, clean chain. If
trouble continues inspect the chain and mating parts for wear,
distortion, or other damage.
19
Slacken the chain and move the adjacent links to one side to
inspect for wear at the contact points. Is wear observed? Is
stretching suspected?
20
Is chain lubricated to manufacturer’s requirement?
Refer to owner’s manual for any additional inspection items:
Comments:
Page 13 of 24
New Haven, Connecticut
Appendix C
Sling Periodic Inspection Checklist
Location:
ID number or identifier:
Inspector Name (print):
Date:
Item (Slings)
Yes
No
N/A
Chain/Slings:
Nicks, cracks, breaks, stretches, distortions, twists, gouges, bends,
heat damage, discoloration, worn or damaged links and components,
Lack of ability of the chain or components to hinge (articulate) freely,
Pitting, corrosion or weld splatter,
Missing or illegible sling identifications,
Other conditions that cause doubt as to the continued safe use of the
sling.
Wire Rope Slings:
Broken wires,
Pitting or corrosion,
Localized wear (shiny worn spots), abrasion or scrapes,
Damage or displacement of end fittings, hooks, rings, links, or collars,
Distortions, kinks, bird caging, crushing, or other evidence of damage
to wire rope structure,
Missing or illegible sling identifications,
Other conditions that cause doubt as to the continued safe use of the
sling.
Synthetic Fiber Rope / Synthetic Webbing Slings:
Melting, charring or burning of any part of the surface,
Snags, punctures, tears, cuts, fraying, broken or worn stitches,
Change in diameter,
Discoloration,
Hard or stiff areas,
Wear or elongation exceeding the amount recommended by the
manufacturer,
Distortion of fittings,
Missing or illegible sling identifications,
Page 14 of 24
New Haven, Connecticut
Other conditions that cause doubt as to the continued safe use of the
sling.
Metal Mesh Slings:
Broken weld or brazed joints,
Broken wire in any part of the mesh,
Abrasion, corrosion, distortion, pitting, twisting, bending, cracking,
gouging of any component,
Lack of flexibility,
Missing or illegible sling identifications,
Other conditions that cause doubt as to the continued safe use of the
sling.
Comments:
Page 15 of 24
New Haven, Connecticut
Appendix D
Examples of Cranes and Hoists
A type of crane where a horizontal member
(jib or boom), supporting a moveable hoist, is
fixed to a wall or to a floor-mounted pillar.
Jib Crane
Wall Crane
A type of crane has a hoist which typically
runs horizontally along rail/s.
Gantry Crane
Semi Gantry Crane
Monorail
Switching Monorail
Page 16 of 24
New Haven, Connecticut
A load lifting system consisting of a hoist
which moves laterally on a beam, girder, or
bridge which in turn moves longitudinally on a
runway made of beams and rails. Loads can
be moved to any point within a rectangle
formed by the bridge span and runway length.
Bridge Crane
Mobile Cranes
ARE NOT COVERED IN THIS PROGRAM
Winches
Follow the manufacturer’s
recommendations
Electric Chain Hoist
Manually operated hoists
Lever Hoist
Chain Fall Hoist
Come Along Hoist
Page 17 of 24
New Haven, Connecticut
Pneumatic Chain Hoist
Electric Wire Rope Hoist
Pneumatic Wire Rope Hoist
Engine Hoists
Follow the manufacturer’s
recommendations
Page 18 of 24
New Haven, Connecticut
Appendix E
Examples of Slings
Alloy Steel Chain
Wire Rope
Metal Mesh
Natural and Synthetic Fiber Rope
Synthetic Web
Page 19 of 24
New Haven, Connecticut
Appendix F
Crane and Hoist Training Certification Form
Name of Trainer (print): _____________________________________________________
(Sign):___________________________________________________________________
Name (Print)
Date of
classroom
training
Date of
hands-
on
training
Date of
Evaluation
(if required)
Signature
Page 20 of 24
New Haven, Connecticut
Appendix G
Safe Work Practices of Cranes, Hoists and Chains/Slings
Cranes and Hoists
General:
A personal protective equipment (PPE) hazard assessment must be performed for
the task. PPE considerations should include a hardhat, safety glasses and safety
shoes.
Rated load capacities, recommended operating speeds, special hazard warnings
and/or instructions, shall be conspicuously posted on all equipment. Instructions or
warnings shall be visible to operators while they are at their control stations.
Do not exceed the rated load capacity of the crane, hoist, slings or other
components. (Keep in mind that the hoist may be higher rated that the rail/beam or
vice versa).
Persons operating the crane, hoist or sling shall inspect all machinery and
equipment prior to each use to make sure it is in safe operating condition.
Belts, gears, shafts, pulleys, sprockets, spindles, drums, fly wheels, chains or other
reciprocating, rotating, or other moving parts or equipment shall be guarded if such
parts are exposed to contact by users, or otherwise create a hazard.
No modifications or additions which affect the capacity or safe operation of the
equipment shall be made without the manufacturer's written approval. If such
modifications or changes are made, the capacity, operation, and maintenance
instruction plates, tags, or decals, shall be changed accordingly. In no case shall the
original safety factor of the equipment be reduced.
Disconnect power to a hoist or crane that is unsafe or in need of repair and tag “Out
of Service, Do Not Use.”
Never operate a hoist or crane that in your opinion is UNSAFE TO OPERATE.
Engaging the Load:
The sling or other device shall be properly seated and secured in the base of the
hook.
The load shall not be applied to the point of the hook or the hook latch.
Before moving the load, the operator shall be sure chains and wire rope are not
kinked or twisted and that multiple part chains or ropes are not twisted about each
other.
The rope or chain must be properly seated on the drum, sheaves or sprockets
before the lift takes place.
Remove slack from the sling, chain or cable before lifting a load.
The hoist must be centered over the load.
Page 21 of 24
New Haven, Connecticut
The operator shall not pick up a load more than the rated load of the hoist or crane.
Specific attention should be given to balancing of the load to prevent slipping.
Moving the Load:
The operator shall not engage in any activity that will divert his/her attention from the
task.
The operator shall respond to signals from a designated person only. However, the
operator shall obey a stop signal at all times, no matter who gives it.
The operator shall make sure the load and hoist will clear all obstacles before
moving or rotating the load.
A person shall be designated to observe clearance of the equipment and give timely
warning for all operations where it is difficult for the operator to maintain the desired
clearance by visual means.
The operator shall inch powered hoists and cranes slowly in engagement with a
load, but should avoid unnecessary inching and quick reversals of direction.
A load shall not be lifted more than a few inches until it is well balanced in the sling
or lifting device.
When lifting loads at or near capacity, brake action shall be tested by lifting the load
a few inches off the surface to verify that the brakes are holding.
On rope hoists, the load shall not be lowered below the point where less than two
wraps of rope remain on each anchorage of the hoist drum, unless a lower limit
device is provided. In this case no less than one wrap may remain on each
anchorage of the hoist drum.
Loads shall not be suspended over personnel, unless unit is specifically designed.
All users shall be kept clear of loads about to be lifted and of suspended loads.
Under no circumstances may anyone ride the hook or load.
Directional movement should be made smoothly and deliberately to avoid swing.
Never pull a hoist by the controller cable.
Contact between trolleys (on two trolley cranes) or between trolleys and stops
should be avoided.
The operator shall not use the upper (or lower, if provided) limit device(s) as a
normal means of stopping the hoist. These are emergency devices only.
Placing the Load:
Never leave the controls unattended while a load is suspended. If it becomes
necessary to leave the controls, lower the load to the floor.
The load block should be positioned above head level when the hoist is not in use.
Page 22 of 24
New Haven, Connecticut
Care shall be exercised when removing a sling from under a landed and blocked
load.
Slings
Slings shall be inspected prior to each use to make sure they are in safe operating
condition.
Slings that are damaged or defective shall not be used.
Slings shall not be shortened with knots or bolts or other makeshift devices.
Sling legs shall not be loaded more than their rated capacities.
Slings used in a basket hitch shall have the loads balanced to prevent slippage.
Slings shall be securely attached to their loads.
Slings shall be padded or protected from sharp edges of their loads.
Suspended loads shall be kept clear of all obstructions.
Hands and fingers shall not be placed between the sling and its load while the sling
is being tightened around the load.
Shock loading is prohibited (abrupt starting or stopping of the load).
A sling shall not be pulled from under a load when the load is resting on the sling.
Slings shall be properly stored when not in use so that they are not subject to
mechanical damage, moisture, corrosives, extreme temperature or kinking.
Page 23 of 24
New Haven, Connecticut
Appendix H
Bridge Crane Operator Evaluation Form
Trainee Name:
Work Area:
Evaluator Name:
Department:
Crane location:
Date:
NOTE: Operators must be evaluated on each type of bridge crane.
Step
Evaluation
N/A
Pass
Fail
1. Pre-use
equipment
inspection
Did operator utilize demonstrate competency to complete
a frequent inspection?
If not, was the operator able to explain all the items they
were looking for?
Was the owner’s manual referenced for any additional
items to be checked?
2. Load
inspection
Was the weight of the load identified as not to exceed the
rated capacity?
Was load properly secured, balanced and stable?
3. Move plan
Was a destination identified?
4. Control
operation
Was operator familiar with all controls?
Was load speed and control satisfactory? (no sudden
stops or acceleration)
5. Worksite
Inspection
Was operator aware of activities in the vicinity including
personnel and equipment?
6. Post move
Was hoist/crane properly stowed? (Hook near bottom of
the hoist)
Were slings properly stored? (not subject to mechanical
damage, moisture, corrosives, extreme temp., or kinking)
7. Comments
Must be included for all “Failed” tasks. If task is failed the evaluator must
explain what was done incorrectly and have the trainee repeat the task
until it is completed correctly.
Trainee Signature:
Evaluator Signature:
Page 24 of 24
New Haven, Connecticut
Appendix I
Instructions for Conducting Bridge Crane Operator Evaluations
(Note: The evaluation can be done in-house using an experienced and competent Yale
person or an outside vendor/safety consultant may be used.)
1. Pre-Requisites:
a. Completed the classroom portion of a crane / hoist training class.
b. Review and become familiar with the Yale Crane, Hoist and Sling written
program.
c. Be experienced with the equipment you will be training on.
d. Review owner’s manual.
2. Make sure the equipment is in safe condition.
3. Make sure the location is safe.
4. Have operator perform each item on the Bridge Crane Operator Evaluation Form.
(Appendix H)
5. Assess the operator’s performance. (Appendix H)
6. Explain any “failed” tasks and have operator repeat task.
7. Sign form.
8. File form with designated person. (Supervisor, work unit safety officer,
department safety officer, etc.)